CFR /  Title 33  /  Part 149  /  Sec. 149.610 What must the District Commander be notified of and when?

The District Commander must be notified of the following: ------------------------------------------------------------------------

The District Commander must be

(a) Construction of a pipeline, At least 30 days before

platform, or single point mooring construction begins.

(SPM) is planned.(b) Construction of a pipeline, Within 24 hours, from the date

platform, or SPM begins. construction begins, that the

lights and sound signals are

in use at the construction

site.(c) A light or sound signal is changed Within 24 hours of the change.

during construction.(d) Lights or sound signals used during Within 24 hours of replacement.

construction of a platform, buoy, or

SPM are replaced by permanent fixtures

to meet the requirements of this part.(e) The first cargo transfer operation At least 60 days before the

begins. operation.------------------------------------------------------------------------