CFR /  Title 40  /  Part 63  /  Sec. 63.11411 What General Provisions apply to this subpart?

(a) You must comply with the requirements of the General Provisions in 40 CFR part 63, subpart A as specified in Table 2 to this subpart.

(b) Your notification of compliance status required by Sec. 63.9(h) must include the following information for a new or existing affected source:

(1) This certification of compliance, signed by a responsible official, for the standards in Sec. 63.11409(a): ``This facility complies with the management practice requirements in Sec. 63.11409(a) for installation and operation of capture systems for each emissions source subject to an emissions limit in Sec. 63.11409(b).''

(2) This certification of compliance by the owner or operator of an existing source (if applicable), signed by a responsible official, for the emissions limits in Sec. 63.11409(b): ``This facility complies with the emissions limits in Sec. 63.11409(b) based on a previous performance test in accordance with Sec. 63.11410(i).''

(3) The process rate for each emissions source subject to an emissions limit in Sec. 63.11409(b) that represents normal and representative production operations.

(4) The procedures used to measure and record the process rate for each emissions source subject to an emissions limit in Sec. 63.11409(b).

(5) This certification of compliance by the owner or operator of an existing affected source, signed by a responsible official, for the control device inspection and maintenance requirements in Sec. 63.11410(b) through (d): ``This facility has conducted an initial inspection of each control device according to the requirements in Sec. 63.11410(b), will conduct periodic inspections and maintenance of control devices in accordance with Sec. 63.11410(c), and will maintain records of each inspection and maintenance action in the logbook required by Sec. 63.11410(d).''

(6) This certification of compliance by the owner or operator of a new affected source, signed by a responsible official, for the bag leak detection system monitoring plan requirement in Sec. 63.11410(g)(2): ``This facility has an approved bag leak detection system monitoring plan in accordance with Sec. 63.11410(g)(2).''

(7) Performance test results for each emissions unit at a new affected source (or each emissions source at an existing affected source if a test is required) in accordance with Sec. 63.11410(j). The performance test results for a new affected source must identify the daily average parameter operating limit for each PM control device.

(8) If applicable, this certification of compliance by the owner or operator of a new or existing source, signed by a responsible official, for the requirement in paragraph (k)(2) of this section to comply with the startup, shutdown, and malfunction provisions in 40 CFR 63.6(e)(3): ``This facility has prepared a startup, shutdown, and malfunction plan in accordance with 40 CFR 63.6(e)(3)''.