(a) You must submit the Initial Notification required by Sec. 63.9(b)(2) no later than 120 days after the applicable compliance date specified in Sec. 63.11464. The Initial Notification must include the information specified in Sec. 63.9(b)(2)(i) through (iv) and may be combined with the Notification of Compliance Status required in Sec. 63.11467 and paragraph (b) of this section if you choose to submit both notifications within 120 days.

(b) You must submit a Notification of Compliance Status in accordance with Sec. 63.9(h) and the requirements in paragraphs (c) and (d) of this section. In addition to the information required in Secs. 63.9(h)(2), 63.11466, and 63.11467, your notification must include the following certification(s) of compliance, as applicable, and signature of a responsible official:

(1) This certification of compliance by the owner or operator of an existing affected source who is relying on a previous performance test: ``This facility complies with the control efficiency requirement [or the outlet concentration limit] in Sec. 63.11465 based on a previous performance test in accordance with Sec. 63.11466.''

(2) This certification of compliance by the owner or operator of any new or existing affected source: ``This facility has conducted an initial inspection of each control device according to the requirements in Sec. 63.11467, will conduct periodic inspections and maintenance of control devices in accordance with Sec. 63.11468, and will maintain records of each inspection and maintenance action required by Sec. 63.11470.''

(3) This certification of compliance by the owner or operator of a new affected source: ``This facility has an approved bag leak detection system monitoring plan in accordance with Sec. 63.11468(c)(2).''

(c) If you own or operate an affected source and are required to conduct a performance test under Sec. 63.11466, you must submit a Notification of Compliance Status, including the performance test results, before the close of business on the 60th day following the completion of the performance test.

(d) If you own or operate an affected source and are not required to conduct a performance test under Sec. 63.11466, you must submit a Notification of Compliance Status, including the results of the previous performance test, no later than 120 days after the applicable compliance date specified in Sec. 63.11464.