(a) Maximum achievable control technology (MACT) standards. (1) The provisions of this subpart pertaining to the MACT standards in Sec. 63.562(b) and (d) of this subpart are applicable to existing and new sources with emissions of 10 or 25 tons, as that term is defined in Sec. 63.561, except as specified in paragraph (d) of this section, and are applicable to new sources with emissions less than 10 and 25 tons, as that term is defined in Sec. 63.561, except as specified in paragraph (d) of this section.

(1) The provisions of this subpart pertaining to the MACT standards in Sec. 63.562(b) and (d) of this subpart are applicable to existing and new sources with emissions of 10 or 25 tons, as that term is defined in Sec. 63.561, except as specified in paragraph (d) of this section, and are applicable to new sources with emissions less than 10 and 25 tons, as that term is defined in Sec. 63.561, except as specified in paragraph (d) of this section.

(2) Existing sources with emissions less than 10 and 25 tons are not subject to the emissions standards in Sec. 63.562(b) and (d).

(3) The recordkeeping requirements of Sec. 63.567(j)(4) and the emission estimation requirements of Sec. 63.565(l) apply to existing sources with emissions less than 10 and 25 tons.

(4) Existing sources with emissions less than 10 and 25 tons must meet the submerged fill standards of 46 CFR 153.282. This submerged fill requirement does not apply to petroleum refineries.

(b) Reasonably available control technology (RACT) standards. (1) The provisions of this subpart pertaining to RACT standards in Sec. 63.562(c) and (d) of this subpart are applicable to sources with throughput of 10 M barrels or 200 M barrels, as that term is defined in Sec. 63.561, except as specified in paragraph (d) of this section.

(1) The provisions of this subpart pertaining to RACT standards in Sec. 63.562(c) and (d) of this subpart are applicable to sources with throughput of 10 M barrels or 200 M barrels, as that term is defined in Sec. 63.561, except as specified in paragraph (d) of this section.

(2) Sources with throughput less than 10 M barrels and 200 M barrels, as that term is defined in Sec. 63.561, are not subject to the emissions standards in Sec. 63.562(c) and (d).

(c) General Provisions applicability. Owners or operators of affected sources, as that term is defined in Sec. 63.561, of this subpart must comply with the requirements of subpart A of this part in accordance with the provisions for applicability of subpart A to this subpart in Table 1 of this section.

(d) Exemptions from MACT and RACT standards. (1) This subpart does not apply to emissions resulting from marine tank vessel loading operations, as that term is defined in Sec. 63.561, of commodities with vapor pressures less than 10.3 kilopascals (kPa) (1.5 pounds per square inch, absolute) (psia) at standard conditions, 20 [deg]C and 760 millimeters Hg (mm Hg).

(1) This subpart does not apply to emissions resulting from marine tank vessel loading operations, as that term is defined in Sec. 63.561, of commodities with vapor pressures less than 10.3 kilopascals (kPa) (1.5 pounds per square inch, absolute) (psia) at standard conditions, 20 [deg]C and 760 millimeters Hg (mm Hg).

(2) The provisions of this subpart pertaining to the MACT standards in Sec. 63.562(b)(2), (3) and (4) and to the RACT standards in Sec. 63.562(c)(3) and (4) do not apply to marine tank vessel loading operations where emissions are reduced by using a vapor balancing system, as that term is defined in Sec. 63.561. The provisions pertaining to the vapor collection system, ship-to-shore compatibility, and vapor tightness of marine tank vessels in Sec. 63.562(b)(1) and (c)(2) do apply.

(3) The provisions of this subpart pertaining to the MACT standards in Sec. 63.562(b)(2), (3), and (4) do not apply to marine tank vessel loading operations that are contiguous with refinery operations at sources subject to and complying with subpart CC of this part, National Emissions Standards for Organic Hazardous Air Pollutants from Petroleum Refineries, except to the extent that any such provisions of this subpart are made applicable by subpart CC of this part.

(4) The provisions of this subpart pertaining to the MACT standards in Sec. 63.562(b) and (d) do not apply to benzene emissions from marine tank vessel loading operations that are subject to and complying with 40 CFR part 61, subpart BB, National Emissions Standards for Benzene Emissions from Benzene Transfer Operations, except that benzene emissions or other HAP emissions (i.e., nonbenzene HAP emissions) from marine tank vessel loading operations that are not subject to subpart BB are subject to the provisions of this subpart.

(5) The provisions of this subpart pertaining to the MACT standards in Sec. 63.562(b) and (d) do not apply to marine tank vessel loading operations at loading berths that only transfer liquids containing organic HAP as impurities, as that term is defined in Sec. 63.561.

(6) The provisions of this subpart do not apply to marine tank vessel loading operations at existing offshore loading terminals, as that term is defined in Sec. 63.561, however existing offshore loading terminals must meet the submerged fill standards of 46 CFR 153.282.

(7) The provisions of this subpart do not apply to ballasting operations, as that term is defined in Sec. 63.561.

(e) Compliance dates--(1) MACT standards compliance dates, except the Valdez Marine Terminal (VMT) source. (i) A new or existing source with emissions of 10 or 25 tons, except the VMT source, and a new source with emissions less than 10 and 25 tons, except the VMT source, that has an initial startup date on or before September 20, 1999 shall comply with the provisions of this subpart pertaining to the MACT standards in Sec. 63.562(b) no later than 4 years after the effective date.

(1) MACT standards compliance dates, except the Valdez Marine Terminal (VMT) source. (i) A new or existing source with emissions of 10 or 25 tons, except the VMT source, and a new source with emissions less than 10 and 25 tons, except the VMT source, that has an initial startup date on or before September 20, 1999 shall comply with the provisions of this subpart pertaining to the MACT standards in Sec. 63.562(b) no later than 4 years after the effective date.

(i) A new or existing source with emissions of 10 or 25 tons, except the VMT source, and a new source with emissions less than 10 and 25 tons, except the VMT source, that has an initial startup date on or before September 20, 1999 shall comply with the provisions of this subpart pertaining to the MACT standards in Sec. 63.562(b) no later than 4 years after the effective date.

(ii) A new source with emissions of 10 or 25 tons, except the VMT source, and a new source with emissions less than 10 and 25 tons, except the VMT source, that has an initial startup date after September 20, 1999 shall comply with provisions of this subpart pertaining to the MACT standards in Sec. 63.562(b) immediately upon startup.

(iii) A source with emissions less than 10 and 25 tons that increases its emissions subsequent to September 20, 1999 such that it becomes a source with emissions of 10 or 25 tons shall comply with the provisions of this subpart pertaining to the MACT standards in Sec. 63.562(b) within 3 years following the exceedance of the threshold level.

(iv) Existing sources with emissions less than 10 and 25 tons, and existing offshore loading terminals, shall comply with the submerged fill requirements in paragraph (a)(4) and (d)(6) of this section by April 23, 2012.

(2) RACT standards compliance dates, except the VMT source. (i) A source with throughput of 10 M barrels or 200 M barrels, except the VMT source, with an initial startup date on or before September 21, 1998 shall comply with Sec. 63.562(c)(1) no later than 2 years after the effective date.

(i) A source with throughput of 10 M barrels or 200 M barrels, except the VMT source, with an initial startup date on or before September 21, 1998 shall comply with Sec. 63.562(c)(1) no later than 2 years after the effective date.

(ii) A source with throughput of 10 M barrels or 200 M barrels, except the VMT source, with an initial startup date on or before September 21, 1998 shall comply with the provisions of this subpart pertaining to the RACT standards in Sec. 63.562(c) other than Sec. 63.562(c)(1), no later than 3 years after the effective date.

(iii) A source with throughput of 10 M barrels or 200 M barrels, except the VMT source, with an initial startup date after September 21, 1998 shall comply with the provisions of this subpart pertaining to the RACT standards in Sec. 63.562(c) immediately upon startup.

(iv) A source with throughput less than 10 M barrels and 200 M barrels that increases its throughput subsequent to September 21, 1998 such that it becomes a source with throughput of 10 M barrels or 200 M barrels shall comply with the provisions of this subpart pertaining to the RACT standards in Sec. 63.562(c) within 3 years following the exceedance of the threshold levels.

(v) A source with throughput of 10 M barrels or 200 M barrels may apply for approval from the Administrator for an extension of the compliance date of up to 1 year if it can demonstrate that the additional time is necessary for installation of the control device.

(3) MACT and RACT compliance dates for the VMT source. The VMT source, as that term is defined in Sec. 63.561, shall comply with the provisions of this subpart pertaining to the MACT and RACT standards in Sec. 63.562(d) no later than 30 months after the effective date.

Table 1 to Sec. 63.560--General Provisions Applicability to Subpart Y------------------------------------------------------------------------

Applies to affected

Reference sources in subpart Y Comment------------------------------------------------------------------------63.1(a)(1).................. Yes................. Additional terms are

defined in Sec.

63.561; when

overlap between

subparts A and Y

occurs, subpart Y

takes precedence.63.1(a)(2).................. Yes63.1(a)(3).................. Yes63.1(a)(4).................. Yes................. Subpart Y clarifies

the applicability

of each paragraph

in subpart A to

sources subject to

subpart Y in this

table..63.1(a)(5)................. No.................. Reserved.63.1(a)(6).................. Yes63.1(a)(7).................. Yes63.1(a)(8).................. Yes63.1(a)(9).................. No.................. Reserved.63.1(a)(10)................. Yes63.1(a)(11)................. Yes................. Sec. 63.567(a) also

allows report

submissions via

facsimile and on

electronic media.63.1(a)(12)................. Yes63.1(a)(13)................. Yes63.1(a)(14)................. Yes63.1(b)(1).................. Yes63.1(b)(2).................. Yes63.1(b)(3).................. No.................. Sec. 63.560

specifies

applicability.63.1(c)(1).................. Yes................. Subpart Y clarifies

the applicability

of each paragraph

in subpart A to

sources subject to

subpart Y in this

table.

63.1(c)(2).................. Yes................. Subpart Y is not

applicable to area

sources.63.1(c)(3).................. No.................. Reserved.63.1(c)(4).................. Yes63.1(c)(5).................. No.................. Sec. 63.560

specifies

applicability.63.1(d)..................... No.................. Reserved.63.1(e)..................... Yes63.2........................ Yes................. Additional terms are

defined in Sec.

63.561; when

overlap between

subparts A and Y

occurs, subpart Y

takes precedence.63.3........................ Yes................. Other units used in

subpart Y are

defined in the text

of subpart Y.63.4(a)(1).................. Yes63.4(a)(2).................. Yes63.4(a)(3).................. Yes63.4(a)(4).................. No.................. Reserved.63.4(a)(5).................. Yes63.4(b)..................... Yes63.4(c)..................... Yes63.5(a)..................... Yes63.5(b)(1)(i)............... Yes63.5(b)(1)(ii).............. No63.5(b)(2).................. No.................. Reserved.63.5(b)(3).................. Yes63.5(b)(4)-(5).............. No63.5(b)(6).................. Yes63.5(c)..................... No.................. Reserved.63.5(d)(1)(i)............... No.................. See Sec.

63.566(b)(2).63.5(d)(1)(ii)(A)(H)........ Yes63.5(d)(1)(ii)(I)........... No.................. Reserved.63.5(d)(1)(ii)(J)........... Yes63.5(d)(1)(iii)............. Yes63.5(d)(2)-(4).............. Yes63.5(e)..................... Yes63.5(f)(1)(i) and (ii)...... Yes63.5(f)(1)(iii) and (iv).... No63.5(f)(2).................. No.................. See Sec. 63.566(c).63.6(a)(1).................. Yes63.6(a)(2).................. No.................. Sec. 63.560

specifies

applicability.63.6(b)(1)-(5).............. No.................. Sec. 63.560(e)

specifies

compliance dates

for sources.63.6(b)(6).................. No.................. Reserved.63.6(b)(7).................. No.................. Sec. 63.560(e)

specifies

compliance dates

for sources.63.6(c)(1).................. No.................. Sec. 63.560(e)

specifies

compliance dates

for sources.63.6(c)(2).................. No63.6(c)(3)-(4).............. No.................. Reserved.63.6(c)(5).................. No.................. Sec. 63.560(e)

specifies

compliance dates

for sources.63.6(d)..................... No.................. Reserved.63.6(e)..................... No.................. See Sec. 63.562(e).63.6(f)(1).................. No.63.6(f)(2)(i)............... Yes63.6(f)(2)(ii).............. No63.6(f)(2)(iii)............. Yes63.6(f)(2)(iv).............. Yes63.6(f)(2)(v)............... No.................. See Sec.

63.562(e)(1).63.6(f)(3).................. Yes63.6(g)..................... Yes63.6(h)..................... No.................. No opacity

monitoring is

required under

subpart Y.63.6(i)(1)-(3).............. Yes63.6(i)(4)(i)(A)............ No63.6(i)(4)(i)(B)............ Yes63.6(i)(4)(ii).............. No63.6(i)(5)-(12)............. Yes63.6(i)(13)................. No63.6(i)(14)................. Yes63.6(i)(15)................. No.................. Reserved.63.6(i)(16)................. Yes63.6(j)..................... Yes63.7(a)(1).................. Yes

63.7(a)(2)(i)-(iv).......... No.................. See Sec.

63.563(b)(1).63.7(a)(2)(v)............... Yes63.7(a)(2)(vi).............. No63.7(a)(2)(vii)-(viii)...... No.................. Reserved.63.7(a)(2)(ix).............. No63.7(a)(3).................. Yes63.7(b)..................... Yes63.7(c)(1)-(2).............. Yes................. The site-specific

test plan must be

submitted only if

requested by the

Administrator.63.7(c)(3)(i)-(ii)(A)....... Yes63.7(c)(3)(ii)(B)........... No.................. See Sec.

63.565(m)(2).63.7(c)(3)(iii)............. Yes63.7(c)(4).................. Yes63.7(d)..................... Yes63.7(e)(1).................. No.................. See 63.563(b)(1).

Any cross reference

to 63.7(e)(1) in

any other general

provision

incorporated by

reference shall be

treated as a cross-

reference to

63.563(b)(1).63.7(e)(2)-(4).............. Yes.63.7(f)..................... Yes63.7(g)(1).................. Yes63.7(g)(2).................. No.................. Reserved.63.7(g)(3).................. Yes63.7(h)..................... Yes63.8(a)(1)-(2).............. Yes63.8(a)(3).................. No.................. Reserved.63.8(a)(4).................. Yes63.8(b)(1).................. Yes63.8(b)(2).................. No63.8(b)(3).................. Yes63.8(c)(1).................. No.63.8(c)(2).................. Yes63.8(c)(3).................. Yes63.8(c)(4).................. No.................. See Sec.

63.564(a)(3).63.8(c)(5).................. No63.8(c)(6).................. Yes................. See also performance

specifications for

continuous

monitoring systems

Sec. 63.564(a)(4).63.8(c)(7)(i)(A)-(B)........ Yes................. See also Sec.

63.564(a)(5).63.8(c)(7)(i)(C)............ No63.8(c)(7)(ii).............. Yes63.8(c)(8).................. No.................. See Sec.

63.564(a)(5).63.8(d)..................... No.................. See Sec.

63.562(e)(2)(iv).63.8(e)(1)-(4).............. Yes63.8(e)(5)(i)............... Yes63.8(e)(5)(ii).............. No63.8(f)(1).................. Yes63.8(f)(2)(i)-(vii)......... Yes63.8(f)(2)(viii)............ No63.8(f)(2)(ix).............. Yes63.8(f)(3)-(6).............. Yes63.8(g)..................... Yes63.9(a)(1).................. Yes63.9(a)(2).................. Yes63.9(a)(3).................. Yes63.9(a)(4).................. Yes63.9(b)(1)(i)............... Yes63.9(b)(1)(ii).............. No.................. See Sec.

63.567(b)(1)63.9(b)(1)(iii)............. Yes63.9(b)(2).................. No.................. See Sec.

63.567(b)(2).63.9(b)(3).................. No.................. See Sec.

63.567(b)(3).63.9(b)(4).................. No.................. See Sec.

63.567(b)(4).63.9(b)(5).................. No.................. See Sec.

63.567(b)(4).63.9(c)..................... No.................. See Sec. 63.567(c).63.9(d)..................... No63.9(e)..................... Yes63.9(f)..................... No63.9(g)(1).................. Yes63.9(g)(2).................. No63.9(g)(3).................. Yes63.9(h)(1)-(3).............. Yes63.9(h)(4).................. No.................. Reserved.

63.9(h)(5)-(6).............. Yes63.9(i)..................... Yes63.9(j)..................... Yes63.10(a).................... Yes63.10(b)(1)................. Yes63.10(b)(2)(i)-(ii)......... No.................. See 63.567(m).63.10(b)(2)(iii)............ Yes.63.10(b)(2)(iv)............. No63.10(b)(2)(v).............. No63.10(b)(2)(vi)-(xiv)....... Yes63.10(b)(3)................. No.................. See Sec.

63.567(j)(4).63.10(c)(1)................. Yes63.10(c)(2)-(4)............. No.................. Reserved.63.10(c)(5)................. Yes63.10(c)(6)................. No.................. See Sec.

63.564(a)(5).63.10(c)(7)................. No63.10(c)(8)................. Yes63.10(c)(9)................. No.................. Reserved.63.10(c)(10)-(11)........... No.................. See 63.567(m) for

reporting

malfunctions. Any

cross-reference to

63.10(c)(10) or

63.10(c)(11) in any

other general

provision

incorporated by

reference shall be

treated as a cross-

reference to

63.567(m).63.10(c)(12)-(13)........... Yes.63.10(c)(14)................ No.................. See Sec.

63.562(d)(2)(iv).63.10(c)(15)................ No63.10(d)(1)-(2)............. Yes63.10(d)(3)................. No.................. See Sec. 63.567(d).63.10(d)(4)................. Yes63.10(d)(5)................. No63.(10)(e)(1)............... Yes63.10(e)(2)(i).............. Yes63.10(e)(2)(ii)............. No63.10(e)(3)(i)-(v).......... No.................. See Sec. 63.567(e)63.10(e)(3)(vi)............. Yes63.10(e)(3)(vii)-(viii)..... No.................. See Sec. 63.567(e)63.10(e)(4)................. No63.10(f).................... Yes63.11....................... Yes63.12-63.15................. Yes ....................------------------------------------------------------------------------ [60 FR 48399, Sept. 19, 1995, as amended at 76 FR 22595, Apr. 21, 2011]