Code of Federal Regulations (alpha)

CFR /  Title 40  /  Part 63  /  Sec. 63.8515 What definitions apply to this subpart?

Terms used in this subpart are defined in the Clean Air Act, in Sec. 63.2, and in this section as follows:

Air pollution control device (APCD) means any equipment that reduces the quantity of a pollutant that is emitted to the air.

Bag leak detection system means an instrument that is capable of monitoring PM loadings in the exhaust of a fabric filter in order to detect bag failures. A bag leak detection system includes, but is not limited to, an instrument that operates on triboelectric, light-scattering, light-transmittance, or other effects to monitor relative PM loadings.

Brick and structural clay products (BSCP) manufacturing facility means a plant site that manufactures brick (including, but not limited to, face brick, structural brick, and brick pavers); clay pipe; roof tile; extruded floor and wall tile; and/or other extruded, dimensional clay products. Brick and structural clay products manufacturing facilities typically process raw clay and shale, form the processed materials into bricks or shapes, and dry and fire the bricks or shapes.

Deviation means any instance in which an affected source subject to this subpart, or an owner or operator of such a source:

(1) Fails to meet any requirement or obligation established by this subpart including, but not limited to, any emission limitation (including any operating limit) or work practice standard;

(2) Fails to meet any term or condition that is adopted to implement an applicable requirement in this subpart for any affected source required to obtain such a permit; or

(3) Fails to meet any emission limitation (including any operating limit) or work practice standard in this subpart during startup, shutdown, or malfunction, regardless of whether or not such failure is permitted by this subpart.

Dry lime injection fabric filter (DIFF) means an APCD that includes continuous injection of hydrated lime or other sorbent into a duct or reaction chamber followed by a fabric filter.

Dry lime scrubber/fabric filter (DLS/FF) means an APCD that includes continuous injection of humidified hydrated lime or other sorbent into a reaction chamber followed by a fabric filter. These systems typically include recirculation of some of the sorbent.

Dry limestone adsorber (DLA) means an APCD that includes a limestone storage bin, a reaction chamber that is essentially a packed tower filled with limestone, and may or may not include a peeling drum that mechanically scrapes reacted limestone to regenerate the stone for reuse.

Emission limitation means any emission limit or operating limit.

Fabric filter means an APCD used to capture PM by filtering a gas stream through filter media; also known as a baghouse.

Initial startup means:

(1) For a new or reconstructed tunnel kiln controlled with a DLA, and for a tunnel kiln that would be considered reconstructed but for Sec. 63.8390(i)(1) or Sec. 63.8390(i)(2), the time at which the temperature in the kiln first reaches 260 C (500 F) and the kiln contains product; or

(2) For a new or reconstructed tunnel kiln controlled with a DIFF, DLS/FF, or WS, the time at which the kiln first reaches a level of production that is equal to 75 percent of the kiln design capacity or 12 months after the affected source begins firing BSCP, whichever is earlier.

Kiln exhaust process stream means the portion of the exhaust from a tunnel kiln that exhausts directly to the atmosphere (or to an APCD), rather than to a sawdust dryer.

Large tunnel kiln means a tunnel kiln (existing, new, or reconstructed) with a design capacity equal to or greater than 9.07 Mg/hr (10 tph) of fired product.

Particulate matter (PM) means, for purposes of this subpart, emissions of PM that serve as a measure of total particulate emissions, as measured by Method 5 (40 CFR part 60, appendix A), and as a surrogate for metal HAP contained in the particulates including, but not limited to, antimony, arsenic, beryllium, cadmium, chromium, cobalt, lead, manganese, mercury, nickel, and selenium.

Plant site means all contiguous or adjoining property that is under common control, including properties that are separated only by a road or other public right-of-way. Common control includes properties that are owned, leased, or operated by the same entity, parent entity, subsidiary, or any combination thereof.

Research and development kiln means any kiln whose purpose is to conduct research and development for new processes and products and is not engaged in the manufacture of products for commercial sale, except in a de minimis manner.

Responsible official means responsible official as defined in 40 CFR 70.2.

Small tunnel kiln means a tunnel kiln (existing, new, or reconstructed) with a design capacity less than 9.07 Mg/hr (10 tph) of fired product.

Startup means the setting in operation of an affected source and starting the production process.

Tunnel kiln means any continuous kiln that is used to fire BSCP. Some tunnel kilns have two process streams, including a process stream that exhausts directly to the atmosphere or to an APCD, and a process stream in which the kiln exhaust is ducted to a sawdust dryer where it is used to dry sawdust before being emitted to the atmosphere.

Tunnel kiln design capacity means the maximum amount of brick, in Mg (tons), that a kiln is designed to produce in one year divided by the number of hours in a year (8,760 hours). If a kiln is modified to increase the capacity, the design capacity is considered to be the capacity following modifications.

Wet scrubber (WS) means an APCD that uses water, which may include caustic additives or other chemicals, as the sorbent. Wet scrubbers may use any of various design mechanisms to increase the contact between exhaust gases and the sorbent.

Sec. Table 1 to Subpart JJJJJ of Part 63--Emission Limits

As stated in Sec. 63.8405, you must meet each emission limit in the following table that applies to you. ------------------------------------------------------------------------

You must meet the Or you must comply

For each . . . following emission with the following

limits . . . . . .------------------------------------------------------------------------1. Existing large tunnel kiln a. HF emissions Reduce

(design capacity =10 must not exceed uncontrolled HF

tph of fired product), 0.029 kilograms emissions by at

excluding any process stream per megagram (kg/ least 90 percent.

that is ducted to a sawdust Mg) (0.057 pounds ..................

dryer prior to July 22, 2002; per ton (lb/ton)) Reduce

or including any process stream of fired product. uncontrolled HCl

that exhausts directly to the b. HCl emissions emissions by at

atmosphere or to an APCD and must not exceed least 30 percent.

any process stream that is 0.13 kg/Mg (0.26 Not applicable.

first ducted to a sawdust on or lb/ton) of fired

after July 22, 2002; each new product.

or reconstructed small tunnel c. PM emissions

kiln (design capacity <10 tph must not exceed

of fired product), including 0.21 kg/Mg (0.42

all process streams; each lb/ton) of fired

tunnel kiln that would be product.

considered reconstructed but

for Sec. 63.8390(i)(1),

including all process streams;

and each large tunnel kiln

previously equipped with a DLA

that would be considered

reconstructed but for Sec.

63.8390(i)(2), including all

process streams.2. New or reconstructed large a. HF emissions Reduce

tunnel kiln, including all must not exceed uncontrolled HF

process streams. 0.029 kg/Mg emissions by at

(0.057 lb/ton) of least 90 percent.

fired product.

b. HCl emissions Reduce

must not exceed uncontrolled HCl

0.028 kg/Mg emissions by at

(0.056 lb/ton) of least 85 percent.

fired product.

c. PM emissions Not applicable.

must not exceed

0.060 kg/Mg (0.12

lb/ton) of fired

product.------------------------------------------------------------------------

Sec. Table 2 to Subpart JJJJJ of Part 63--Operating Limits

As stated in Sec. 63.8405, you must meet each operating limit in the following table that applies to you. ------------------------------------------------------------------------

For each . . . You must . . .------------------------------------------------------------------------1. Kiln equipped with a DLA....... a. Maintain the average pressure

drop across the DLA for each 3-hour

block period at or above the

average pressure drop established

during the performance test; and

b. Maintain an adequate amount of

limestone in the limestone hopper,

storage bin (located at the top of

the DLA), and DLA at all times;

maintain the limestone feeder

setting at or above the level

established during the performance

test; and

c. Use the same grade of limestone

from the same source as was used

during the performance test;

maintain records of the source and

grade of limestone; and

d. Maintain no VE from the DLA

stack.2. Kiln equipped with a DIFF or a. If you use a bag leak detection

DLS/FF. system, initiate corrective action

within 1 hour of a bag leak

detection system alarm and complete

corrective actions in accordance

with your OM&M; plan; operate and

maintain the fabric filter such

that the alarm is not engaged for

more than 5 percent of the total

operating time in a 6-month block

reporting period; or maintain no VE

from the DIFF or DLS/FF stack; and

b. Maintain free-flowing lime in the

feed hopper or silo and to the APCD

at all times for continuous

injection systems; maintain the

feeder setting at or above the

level established during the

performance test for continuous

injection systems.3. Kiln equipped with a WS........ a. Maintain the average scrubber

pressure drop for each 3-hour block

period at or above the average

pressure drop established during

the performance test; and

b. Maintain the average scrubber

liquid pH for each 3-hour block

period at or above the average

scrubber liquid pH established

during the performance test; and

c. Maintain the average scrubber

liquid flow rate for each 3-hour

block period at or above the

average scrubber liquid flow rate

established during the performance

test; and

d. If chemicals are added to the

scrubber water, maintain the

average scrubber chemical feed rate

for each 3-hour block period at or

above the average scrubber chemical

feed rate established during the

performance test.------------------------------------------------------------------------

Sec. Table 3 to Subpart JJJJJ of Part 63--Requirements for Performance

Tests

As stated in Sec. 63.8445, you must conduct each performance test in the following table that applies to you. ----------------------------------------------------------------------------------------------------------------

According to the

For each . . . You must . . . Using . . . following requirements

. . .----------------------------------------------------------------------------------------------------------------1. Kiln.............................. a. Select locations of Method 1 or 1A of 40 Sampling sites must be

sampling ports and the CFR part 60, appendix located at the outlet

number of traverse A. of the APCD and prior

points. to any releases to the

atmosphere for all

affected sources. If

you choose to meet the

percent emission

reduction requirements

for HF or HCl, a

sampling site must

also be located at the

APCD inlet.

b. Determine velocities Method 2 of 40 CFR part You may use Method 2A,

and volumetric flow 60, appendix A. 2C, 2D, 2F, or 2G of

rate. 40 CFR part 60,

appendix A, as

appropriate, as an

alternative to using

Method 2 of 40 CFR

part 60, appendix A.

c. Conduct gas Method 3 of 40 CFR part You may use Method 3A

molecular weight 60, appendix A. or 3B of 40 CFR part

analysis. 60, appendix A, as

appropriate, as an

alternative to using

Method 3 of 40 CFR

part 60, appendix A.

d. Measure moisture Method 4 of 40 CFR part .......................

content of the stack 60, appendix A.

gas.

e. Measure HF and HCl Method 26A of 40 CFR Conduct the test while

emissions. part 60, appendix A; operating at the

or maximum production

level. You may use

Method 26 of 40 CFR

part 60, appendix A,

as an alternative to

using Method 26A of 40

CFR part 60, appendix

A, when no acid PM

(e.g., HF or HCl

dissolved in water

droplets emitted by

sources controlled by

a WS) is present.

Method 320 of 40 CFR Conduct the test while

part 63, appendix A. operating at the

maximum production

level. When using

Method 320 of 40 CFR

part 63, appendix A,

you must follow the

analyte spiking

procedures of section

13 of Method 320 of 40

CFR part 63, appendix

A, unless you can

demonstrate that the

complete spiking

procedure has been

conducted at a similar

source.

f. Measure PM Method 5 of 40 CFR part Conduct the test while

emissions. 60, appendix A. operating at the

maximum production

level.2. Kiln that is complying with Determine the Production data You must measure and

production-based emission limits. production rate during collected during the record the production

each test run in order performance tests rate, on a fired-

to determine (e.g., no. of pushes product basis, of the

compliance with per hour, no. of affected source for

production-based bricks per kiln car, each of the three test

emission limits. weight of a typical runs.

fired brick).3. Kiln equipped with a DLA.......... a. Establish the Data from the pressure You must continuously

operating limit for drop measurement measure the pressure

the average pressure device during the drop across the DLA,

drop across the DLA. performance test. determine and record

the block average

pressure drop values

for the three test

runs, and determine

and record the 3-hour

block average of the

recorded pressure drop

measurements for the

three test runs.

b. Establish the Data from the limestone You must ensure that

operating limit for feeder during the you maintain an

the limestone feeder performance test. adequate amount of

setting. limestone in the

limestone hopper,

storage bin (located

at the top of the

DLA), and DLA at all

times during the

performance test. You

must establish your

limestone feeder

setting one week prior

to the performance

test and maintain the

feeder setting for the

one-week period that

precedes the

performance test and

during the performance

test.

c. Document the source Records of limestone

and grade of limestone purchase.

used.

4. Kiln equipped with a DIFF or DLS/ Establish the operating Data from the lime For continuous lime

FF. limit for the lime feeder during the injection systems, you

feeder setting. performance test. must ensure that lime

in the feed hopper or

silo and to the APCD

is free-flowing at all

times during the

performance test and

record the feeder

setting for the three

test runs. If the feed

rate setting varies

during the three test

runs, determine and

record the average

feed rate from the

three test runs.5. Kiln equipped with a WS........... a. Establish the Data from the pressure You must continuously

operating limit for drop measurement measure the scrubber

the average scrubber device during the pressure drop,

pressure drop. performance test. determine and record

the block average

pressure drop values

for the three test

runs, and determine

and record the 3-hour

block average of the

recorded pressure drop

measurements for the

three test runs.

b. Establish the Data from the pH You must continuously

operating limit for measurement device measure the scrubber

the average scrubber during the performace liquid pH, determine

liquid pH. test. and record the block

average pH values for

the three test runs,

and determine and

record the 3-hour

block average of the

recorded pH

measurements for the

three test runs.

c. Establish the Data from the flow rate You must continuously

operating limit for measurement device measure the scrubber

the average scrubber during the performance liquid flow rate,

liquid flow rate. test. determine and record

the block average flow

rate values for the

three test runs, and

determine and record

the 3-hour block

average of the

recorded flow rate

measurements for the

three test runs.6. Kiln equipped with a WS that Establish the operating Data from the chemical You must continuously

includes chemical addition to the limit for the average feed rate measurement measure the scrubber

water. scrubber chemical feed device during the chemical feed rate,

rate. performance test. determine and record

the block average

chemical feed rate

values for the three

test runs, and

determine and record

the 3-hour block

average of the

recorded chemical feed

rate measurements for

the three test runs.----------------------------------------------------------------------------------------------------------------

Sec. Table 4 to Subpart JJJJJ of Part 63--Initial Compliance With

Emission Limitations

As stated in Sec. 63.8455, you must demonstrate initial compliance with each emission limitation that applies to you according to the following table: ------------------------------------------------------------------------

You have

For the following demonstrated

For each . . . emission initial compliance

limitation . . . if . . .------------------------------------------------------------------------1. Existing large tunnel kiln a. HF emissions i. The HF

(design capacity =10 must not exceed emissions

tph of fired product), 0.029 kg/Mg measured using

excluding any process stream (0.057 lb/ton) of Method 26A of 40

that is ducted to a sawdust fired product; or CFR part 60,

dryer prior to July 22, 2002; uncontrolled HF appendix A or

or including any process stream emissions must be Method 320 of 40

that exhausts directly to the reduced by at CFR part 63,

atmosphere or to an APCD and least 90 percent; appendix A over

any process stream that is and the period of the

first ducted to a sawdust dryer initial

on or after July 22, 2002; each performance test,

new or reconstructed small according to the

tunnel kiln (design capacity calculations in

<10 tph of fired product), Sec.

including all process streams; 63.8445(g)(1), do

each tunnel kiln that would be not exceed 0.029

considered reconstructed but kg/Mg (0.057 lb/

for Sec. 63.8390(i)(1), ton); or

including all process streams; uncontrolled HF

and each large tunnel kiln emissions

previously equipped with a DLA measured using

that would be considered Method 26A of 40

reconstructed but for Sec. CFR part 60,

63.8390(i)(2), including all appendix A or

process streams. Method 320 of 40

CFR part 63,

appendix A over

the period of the

initial

performance test

are reduced by at

least 90 percent,

according to the

calculations in

Sec.

63.8445(g)(2);

and

ii. You establish

and have a record

of the operating

limits listed in

Table 2 to this

subpart over the

3-hour

performance test

during which HF

emissions did not

exceed 0.029 kg/

Mg (0.057 lb/ton)

or uncontrolled

HF emissions were

reduced by at

least 90 percent.

b. HCl emissions i. The HCl

must not exceed emissions

0.13 kg/Mg (0.26 measured using

lb/ton) of fired Method 26A of 40

product; or CFR part 60,

uncontrolled HCl appendix A or

emissions must be Method 320 of 40

reduced by at CFR part 63,

least 30 percent; appendix A over

and the period of the

initial

performance test,

according to the

calculations in

Sec.

63.8445(g)(1), do

not exceed 0.13

kg/Mg (0.26 lb/

ton); or

uncontrolled HCl

emissions

measured using

Method 26A of 40

CFR part 60,

appendix A or

Method 320 of 40

CFR part 63,

appendix A over

the period of the

initial

performance test

are reduced by at

least 30 percent,

according to the

calculations in

Sec.

63.8445(g)(2);

and

ii. You establish

and have a record

of the operating

limits listed in

Table 2 to this

subpart over the

3-hour

performance test

during which HCl

emissions did not

exceed 0.13 kg/Mg

(0.26 lb/ton) or

uncontrolled HCl

emissions were

reduced by at

least 30 percent.

c. PM emissions i. The PM

must not exceed emissions

0.21 kg/Mg (0.42 measured using

lb/ton) of fired Method 5 of 40

product. CFR part 60,

appendix A, over

the period of the

initial

performance test,

according to the

calculations in

Sec.

63.8445(g)(1), do

not exceed 0.21

kg/Mg (0.42 lb/

ton); and

ii. You establish

and have a record

of the operating

limits listed in

Table 2 to this

subpart over the

3-hour

performance test

during which PM

emissions did not

exceed 0.21 kg/Mg

(0.42 lb/ton).

2. New or reconstructed large a. HF emissions i. The HF

tunnel kiln, including all must not exceed emissions

process streams. 0.029 kg/Mg measured using

(0.057 lb/ton) of Method 26A of 40

fired product; or CFR part 60,

uncontrolled HF appendix A or

emissions must be Method 320 of 40

reduced by at CFR part 63,

least 90 percent; appendix A over

and the period of the

initial

performance test,

according to the

calculations in

Sec.

63.8445(g)(1), do

not exceed 0.029

kg/Mg (0.057 lb/

ton); or

uncontrolled HF

emissions

measured using

Method 26A of 40

CFR part 60,

appendix A or

Method 320 of 40

CFR part 63,

appendix A over

the period of the

initial

performance test

are reduced by at

least 90 percent,

according to the

calculations in

Sec.

63.8445(g)(2);

and

ii. You establish

and have a record

of the operating

limits listed in

Table 2 to this

subpart over the

3-hour

performance test

during which HF

emissions did not

exceed 0.029 kg/

Mg (0.057 lb/ton)

or uncontrolled

HF emissions were

reduced by at

least 90 percent.

b. HCl emissions i. The HCl

must not exceed emissions

0.028 kg/Mg measured using

(0.056 lb/ton) of Method 26A of 40

fired product; or CFR part 60,

uncontrolled HCl appendix A or

emissions must be Method 320 of 40

reduced by at CFR part 63,

least 85 percent; appendix A over

and the period of the

initial

performance test,

according to the

calculations in

Sec.

63.8445(g)(1), do

not exceed 0.028

kg/Mg (0.056 lb/

ton); or

uncontrolled HCl

emissions

measured using

Method 26A of 40

CFR part 60,

appendix A or

Method 320 of 40

CFR part 63,

appendix A over

the period of the

initial

performance test

are reduced by at

least 85 percent,

according to the

calculations in

Sec.

63.8445(g)(2);

and

ii. You establish

and have a record

of the operating

limits listed in

Table 2 to this

subpart over the

3-hour

performance test

during which HCl

emissions did not

exceed 0.028 kg/

Mg (0.056 lb/ton)

or uncontrolled

HCl emissions

were reduced by

at least 85

percent.

c. PM emissions i. The PM

must not exceed emissions

0.060 kg/Mg (0.12 measured using

lb/ton) of fired Method 5 of 40

product. CFR part 60,

appendix A, over

the period of the

initial

performance test,

according to the

calculations in

Sec.

63.8445(g)(1), do

not exceed 0.060

kg/Mg (0.12 lb/

ton); and

ii. You establish

and have a record

of the operating

limits listed in

Table 2 to this

subpart over the

3-hour

performance test

during which PM

emissions did not

exceed 0.060 kg/

Mg (0.12 lb/ton).------------------------------------------------------------------------

Sec. Table 5 to Subpart JJJJJ of Part 63--Continuous Compliance With

Emission Limits and Operating Limits

As stated in Sec. 63.8470, you must demonstrate continuous compliance with each emission limit and operating limit that applies to you according to the following table: ------------------------------------------------------------------------

For the following

emission limits You must demonstrate

For each . . . and operating continuous compliance

limits . . . by . . .

------------------------------------------------------------------------1. Kiln equipped with a DLA... Each emission i. Collecting the DLA

limit in Table 1 pressure drop data

to this subpart according to Sec.

and each 63.8450(a); reducing

operating limit the DLA pressure

in Item 1 of drop data to 3-hour

Table 2 to this block averages

subpart for according to Sec.

kilns equipped 63.8450(a);

with a DLA. maintaining the

average pressure

drop across the DLA

for each 3-hour

block period at or

above the average

pressure drop

established during

the performance

test; and

ii. Verifying that

the limestone hopper

and storage bin

(located at the top

of the DLA) contain

adequate limestone

by performing a

daily visual check;

and

iii. Recording the

limestone feeder

setting daily to

verify that the

feeder setting is

being maintained at

or above the level

established during

the performance

test; and

iv. Using the same

grade of limestone

from the same source

as was used during

the performance

test; maintaining

records of the

source and type of

limestone; and

v. Performing VE

observations of the

DLA stack at the

frequency specified

in Sec. 63.8470(g)

using Method 22 of

40 CFR part 60,

appendix A;

maintaining no VE

from the DLA stack.2. Kiln equipped with a DIFF Each emission i. If you use a bag

or DLS/FF. limit in Table 1 leak detection

to this subpart system, initiating

and each corrective action

operating limit within 1 hour of a

in Item 2 of bag leak detection

Table 2 to this system alarm and

subpart for completing

kilns equipped corrective actions

with DIFF or DLS/ in accordance with

FF. your OM&M; plan;

operating and

maintaining the

fabric filter such

that the alarm is

not engaged for more

than 5 percent of

the total operating

time in a 6-month

block reporting

period; in

calculating this

operating time

fraction, if

inspection of the

fabric filter

demonstrates that no

corrective action is

required, no alarm

time is counted; if

corrective action is

required, each alarm

is counted as a

minimum of 1 hour;

if you take longer

than 1 hour to

initiate corrective

action, the alarm

time is counted as

the actual amount of

time taken by you to

initiate corrective

action; or

performing VE

observations of the

DIFF or DLS/FF stack

at the frequency

specified in Sec.

63.8470(g) using

Method 22 of 40 CFR

part 60, appendix A;

maintaining no VE

from the DIFF or DLS/

FF stack; and

ii. Verifying that

lime is free-flowing

via a load cell,

carrier gas/lime

flow indicator,

carrier gas pressure

drop measurement

system, or other

system; recording

all monitor or

sensor output, and

if lime is found not

to be free flowing,

promptly initiating

and completing

corrective actions

in accordance with

your OM&M; plan;

recording the feeder

setting once during

each shift of

operation to verify

that the feeder

setting is being

maintained at or

above the level

established during

the performance

test.3. Kiln equipped with a WS.... Each emission i. Collecting the

limit in Table 1 scrubber pressure

to this subpart drop data according

and each to Sec.

operating limit 63.8450(a); reducing

in Item 3 of the scrubber

Table 2 to this pressure drop data

subpart for to 3-hour block

kilns equipped averages according

with WS. to Sec.

63.8450(a);

maintaining the

average scrubber

pressure drop for

each 3-hour block

period at or above

the average pressure

drop established

during the

performance test;

and

ii. Collecting the

scrubber liquid pH

data according to

Sec. 63.8450(a);

reducing the

scrubber liquid pH

data to 3-hour block

averages according

to Sec.

63.8450(a);

maintaining the

average scrubber

liquid pH for each 3-

hour block period at

or above the average

scrubber liquid pH

established during

the performance

test; and

iii. Collecting the

scrubber liquid flow

rate data according

to Sec.

63.8450(a); reducing

the scrubber liquid

flow rate data to 3-

hour block averages

according to Sec.

63.8450(a);

maintaining the

average scrubber

liquid flow rate for

each 3-hour block

period at or above

the average scrubber

liquid flow rate

established during

the performance

test; and

iv. If chemicals are

added to the

scrubber water,

collecting the

scrubber chemical

feed rate data

according to Sec.

63.8450(a); reducing

the scrubber

chemical feed rate

data to 3-hour block

averages according

to Sec.

63.8450(a);

maintaining the

average scrubber

chemical feed rate

for each 3-hour

block period at or

above the average

scrubber chemical

feed rate

established during

the performance

test.------------------------------------------------------------------------

Sec. Table 6 to Subpart JJJJJ of Part 63--Requirements for Reports

As stated in Sec. 63.8485, you must submit each report that applies to you according to the following table: ----------------------------------------------------------------------------------------------------------------

You must submit the report

You must submit . . . The report must contain . . . . . .----------------------------------------------------------------------------------------------------------------1. A compliance report.................. a. If there are no deviations from any Semiannually according to

emission limitations (emission limits, the requirements in Sec.

operating limits) that apply to you, a 63.8485(b).

statement that there were no deviations

from the emission limitations during the

reporting period. If there were no

periods during which the CMS was out-of-

control as specified in your OM&M; plan, a

statement that there were no periods

during which the CMS was out- of-control

during the reporting period.

b. If you have a deviation from any Semiannually according to

emission limitation (emission limit, the requirements in Sec.

operating limit) during the reporting 63.8485(b).

period, the report must contain the

information in Sec. 63.8485(d) or (e).

If there were periods during which the

CMS was out-of-control, as specified in

your OM&M; plan, the report must contain

the information in Sec. 63.8485(e).

c. If you had a startup, shutdown or Semiannually according to

malfunction during the reporting period the requirements in Sec.

and you took actions consistent with your 63.8485(b).

SSMP, the compliance report must include

the information in Sec. 63.10(d)(5)(i).2. An immediate startup, shutdown, and a. Actions taken for the event according By fax or telephone within

malfunction report if you took actions to the requirements in Sec. 2 working days after

during a startup, shutdown, or 63.10(d)(5)(ii). starting actions

malfunction during the reporting period inconsistent with the

that are not consistent with your SSMP. plan.

b. The information in Sec. By letter within 7 working

63.10(d)(5)(ii). days after the end of the

event unless you have

made alternative

arrangements with the

permitting authority.----------------------------------------------------------------------------------------------------------------

Sec. Table 7 to Subpart JJJJJ of Part 63--Applicability of General

Provisions to Subpart JJJJJ

As stated in Sec. 63.8505, you must comply with the General Provisions in Sec. Sec. 63.1 through 63.15 that apply to you according to the following table: ----------------------------------------------------------------------------------------------------------------

Applies to subpart

Citation Subject Brief description JJJJJ----------------------------------------------------------------------------------------------------------------Sec. 63.1....................... Applicability......... Initial applicability Yes.

determination; applicability

after standard established;

permit requirements;

extensions, notifications.Sec. 63.2....................... Definitions........... Definitions for part 63 Yes.

standards.Sec. 63.3....................... Units and Units and abbreviations for Yes.

Abbreviations. part 63 standards.Sec. 63.4....................... Prohibited Activities. Compliance date; Yes.

circumvention; severability.Sec. 63.5....................... Construction/ Applicability; applications; Yes.

Reconstruction. approvals.

Sec. 63.6(a).................... Applicability......... General Provisions (GP) apply Yes.

unless compliance extension;

GP apply to area sources that

become major.Sec. 63.6(b)(1)-(4)............. Compliance Dates for Standards apply at effective Yes.

New and Reconstructed date; 3 years after effective

sources. date; upon startup; 10 years

after construction or

reconstruction commences for

section 112(f).Sec. 63.6(b)(5)................. Notification.......... Must notify if commenced Yes.

construction or

reconstructionafter proposal.Sec. 63.6(b)(6)................. [Reserved].Sec. 63.6(b)(7)................. Compliance Dates for Area sources that become major Yes.

New and Reconstructed must comply with major source

area Sources That standards immediately upon

Become Major. becoming major, regardless of

whether required to comply

when they were area sources.Sec. 63.6(c)(1)-(2)............. Compliance Dates for Comply according to date in Yes.

Existing Sources. subpart, which must be no

later than 3 years after

effective date; for section

112(f) standards, comply

within 90 days of effective

date unless compliance

extension.Sec. 63.6(c)(3)-(4)............. [Reserved]............Sec. 63.6(c)(5)................. Compliance Dates for Area sources that become major Yes.

Existing area Sources must comply with major source

That Become Major. standards by date indicated

in subpart or by equivalent

time period (for example, 3

years).Sec. 63.6(d).................... [Reserved].Sec. 63.6(e)(1)-(2)............. Operation & Operate to minimize emissions Yes.

Maintenance. at all times; correct

malfunctions as soon as

practicable; requirements

independently enforceable;

information Administrator

will use to determine if

operation and maintenance

requirements were met.Sec. 63.6(e)(3)................. Startup, Shutdown, and Requirement for startup, Yes.

Malfunction Plan shutdown, and malfunction

(SSMP). (SSM) and SSMP; content of

SSMP.Sec. 63.6(f)(1)................. Compliance Except You must comply with emission Yes.

During SSM. standards at all times except

during SSM.Sec. 63.6(f)(2)-(3)............. Methods for Compliance based on Yes.

Determining performance test, operation

Compliance. and maintenance plans,

records, inspection.Sec. 63.6(g).................... Alternative Standard.. Procedures for getting an Yes.

alternative standard.Sec. 63.6(h).................... Opacity/VE Standards.. Requirements for opacity and No, not applicable.

VE standards.Sec. 63.6(i).................... Compliance Extension.. Procedures and criteria for Yes.

Administrator to grant

compliance extension.Sec. 63.6(j).................... Presidential President may exempt source Yes.

Compliance Exemption. category.Sec. 63.7(a)(1)-(2)............. Performance Test Dates Dates for conducting initial Yes.

performance testing and other

compliance demonstrations;

must conduct 180 days after

first subject to rule.Sec. 63.7(a)(3)................. Section 114 Authority. Administrator may require a Yes.

performance test under CAA

section 114 at any time.Sec. 63.7(b)(1)................. Notification of Must notify Administrator 60 Yes.

Performance Test. days before the test.Sec. 63.7(b)(2)................. Notification of Must notify Administrator 5 Yes.

Rescheduling. days before scheduled date of

rescheduled date.Sec. 63.7(c).................... Quality Assurance(QA)/ Requirements; test plan Yes.

Test Plan. approval procedures;

performance audit

requirements; internal and

external QA procedures for

testing.Sec. 63.7(d).................... Testing Facilities.... Requirements for testing Yes.

facilities.Sec. 63.7(e)(1)................. Conditions for Performance tests must be No, Sec. 63.8445

Conducting conducted under specifies

Performance Tests. representative conditions. requirements.

Cannot conduct performance Yes.

tests during SSM; not a

violation to exceed standard

during SSM.Sec. 63.7(e)(2)-(3)............. Conditions for Must conduct according to Yes.

Conducting subpart and EPA test methods

Performance Tests. unless Administrator approves

alternative; must have at

least three test runs of at

least 1 hour each; compliance

is based on arithmetic mean

of three runs; conditions

when data from an additional

test run can be used.Sec. 63.7(f).................... Alternative Test Procedures by which Yes.

Method. Administrator can grant

approval to use an

alternative test method.

Sec. 63.7(g).................... Performance Test Data Must include raw data in Yes.

Analysis. performance test report; must

submit performance test data

60 days after end of test

with the notification of

compliance status.Sec. 63.7(h).................... Waiver of Tests....... Procedures for Administrator Yes.

to waive performance test.Sec. 63.8(a)(1)................. Applicability of Subject to all monitoring Yes.

Monitoring requirements in subpart.

Requirements.Sec. 63.8(a)(2)................. Performance Performance Specifications in Yes.

Specifications. appendix B of 40 CFR part 60

apply.Sec. 63.8(a)(3)................. [Reserved]............Sec. 63.8(a)(4)................. Monitoring with Flares Requirements for flares in No, not applicable.

Sec. 63.11 apply.Sec. 63.8(b)(1)................. Monitoring............ Must conduct monitoring Yes.

according to standard unless

Administrator approves

alternative.Sec. 63.8(b)(2)-(3)............. Multiple Effluents and Specific requirements for Yes.

Multiple Monitoring installing and reporting on

Systems. monitoring systems.Sec. 63.8(c)(1)................. Monitoring System Maintenance consistent with Yes.

Operation and good air pollution control

Maintenance. practices.Sec. 63.8(c)(1)(i).............. Routine and Reporting requirements for SSM Yes.

Predictable SSM. when action is described in

SSMP.Sec. 63.8(c)(1)(ii)............. SSM not in SSMP....... Reporting requirements for SSM Yes.

when action is not described

in SSMP.Sec. 63.8(c)(1)(iii)............ Compliance with How Administrator determines Yes.

Operation and if source complying with

Maintenance operation and maintenance

Requirements. requirements.Sec. 63.8(c)(2)-(3)............. Monitoring System Must install to get Yes.

Installation. representative emission and

parameter measurements.Sec. 63.8(c)(4)................. CMS Requirements...... Requirements for CMS.......... No, Sec. Sec.

63.8425 and 63.8465

specify

requirements.Sec. 63.8(c)(5)................. Continuous Opacity COMS minimum procedures....... No, not applicable.

Monitoring System

(COMS) Minimum

Procedures.Sec. 63.8(c)(6)................. CMS Requirements...... Zero and high level No, Sec. 63.8425

calibration check specifies

requirements. requirements.Sec. 63.8(c)(7)-(8)............. CMS Requirements...... Out-of-control periods........ No, Sec. 63.8425

specifies

requirements.Sec. 63.8(d).................... CMS Quality Control... Requirements for CMS quality No, Sec. 63.8425

control. specifies

requirements.Sec. 63.8(e).................... CMS Performance Requirements for CMS No, Sec. 63.8425

Evaluation. performance evaluation. specifies

requirements.Sec. 63.8(f)(1)-(5)............. Alternative Monitoring Procedures for Administrator Yes.

Method. to approve alternative

monitoring.Sec. 63.8(f)(6)................. Alternative to Procedures for Administrator No, not applicable.

Relative Accuracy to approve alternative

Test. relative accuracy test for

continuous emissions

monitoring systems (CEMS).Sec. 63.8(g).................... Data Reduction........ COMS and CEMS data reduction No, not applicable.

requirements.Sec. 63.9(a).................... Notification Applicability; State Yes.

Requirements. delegation.Sec. 63.9(b).................... Initial Notifications. Requirements for initial Yes.

notifications.Sec. 63.9(c).................... Request for Compliance Can request if cannot comply Yes.

Extension. by date or if installed BACT/

LAER.Sec. 63.9(d).................... Notification of For sources that commence Yes.

Special Compliance construction between proposal

Requirements for New and promulgation and want to

Source. comply 3 years after

effective date.Sec. 63.9(e).................... Notification of Notify Administrator 60 days Yes.

Performance Test. prior.Sec. 63.9(f).................... Notification of VE/ Notify Administrator 30 days No, not applicable.

Opacity Test. prior.Sec. 63.9(g)(1)................. Additional Notification of performance Yes.

Notifications When evaluation.

Using CMS.Sec. 63.9(g)(2)-(3)............. Additional Notification of COMS data use; No, not applicable.

Notifications When notification that relative

Using CMS. accuracy alternative

criterion were exceeded.Sec. 63.9(h).................... Notification of Contents; submittal Yes.

Compliance Status. requirements.Sec. 63.9(i).................... Adjustment of Procedures for Administrator Yes.

Submittal Deadlines. to approve change in when

notifications must be

submitted.Sec. 63.9(j).................... Change in Previous Must submit within 15 days Yes.

Information. after the change.Sec. 63.10(a)................... Recordkeeping/ Applicability; general Yes.

Reporting. information.

Sec. 63.10(b)(1)................ General Recordkeeping General requirements.......... Yes.

Requirements.Sec. 63.10(b)(2)(i)-(v)......... Records Related to SSM Requirements for SSM records.. Yes.Sec. 63.10(b)(2)(vi)-(xii) and CMS Records........... Records when CMS is Yes.

(xiv). malfunctioning, inoperative

or out-of-control.Sec. 63.10(b)(2)(xiii).......... Records............... Records when using alternative No, not applicable.

to relative accuracy test.Sec. 63.10(b)(3)................ Records............... Applicability Determinations.. Yes.Sec. 63.10(c)(1)-(15)........... Records............... Additional records for CMS.... No, Sec. Sec.

63.8425 and 63.8490

specify

requirements.Sec. 63.10(d)(1) and (2)........ General Reporting Requirements for and Yes.

Requirements. reporting; performance test

results reporting.Sec. 63.10(d)(3)................ Reporting Opacity or Requirements for reporting No, not applicable.

VE Observations. opacity and VE.Sec. 63.10(d)(4)................ Progress Reports...... Must submit progress reports Yes.

on schedule if under

compliance extension.Sec. 63.10(d)(5)................ SSM Reports........... Contents and submission....... Yes.Sec. 63.10(e)(1)-(3)............ Additional CMS Reports Requirements for CMS reporting No, Sec. Sec.

63.8425 and 63.8485

specify

requirements.Sec. 63.10(e)(4)................ Reporting COMS data... Requirements for reporting No, not applicable.

COMS data with performance

test data.Sec. 63.10(f)................... Waiver for Procedures for Administrator Yes.

Recordkeeping/ to waive.

Reporting.Sec. 63.11...................... Flares................ Requirement for flares........ No, not applicable.Sec. 63.12...................... Delegation............ State authority to enforce Yes.

standards.Sec. 63.13...................... Addresses............. Addresses for reports, Yes.

notifications, requests.Sec. 63.14...................... Incorporation by Materials incorporated by Yes.

Reference. reference.Sec. 63.15...................... Availability of Information availability; Yes.

Information. confidential information.----------------------------------------------------------------------------------------------------------------

Subpart KKKKK_National Emission Standards for Hazardous Air Pollutants

for Clay Ceramics Manufacturing

Source: 68 FR 26738, May 16, 2003, unless otherwise noted.

What This Subpart Covers