Code of Federal Regulations (alpha)

CFR /  Title 47  /  Part 2  /  Sec. 2.950 Transition periods.

(a) As of July 13, 2015 the Commission will no longer accept applications for Commission issued grants of equipment certification.

(b) Prior to September 15, 2015 a TCB shall be accredited to either ISO/IEC Guide 65 or ISO/IEC 17065 (incorporated by reference, see Sec. 2.910). On or after September 15, 2015 a TCB shall be accredited to ISO/IEC 17065.

(c) Prior to September 15, 2015 an organization accrediting the prospective telecommunication certification body shall be capable of meeting the requirements and conditions of ISO/IEC Guide 61 or ISO/IEC 17011 (incorporated by reference, see Sec. 2.910). On or after September 15, 2015 an organization accrediting the prospective telecommunication certification body shall be capable of meeting the requirements and conditions of ISO/IEC 17011.

(d) Prior to September 15, 2015 an organization accrediting the prospective accredited testing laboratory shall be capable of meeting the requirements and conditions of ISO/IEC Guide 58 or ISO/IEC 17011. On or after September 15, 2015 an organization accrediting the prospective accredited testing laboratory shall be capable of meeting the requirements and conditions of ISO/IEC 17011.

(e) The Commission will no longer accept applications for Sec. 2.948 test site listing as of July 13, 2015. Laboratories that are listed by the Commission under the Sec. 2.948 process will remain listed until the sooner of their expiration date or July 13, 2016 and may continue to submit test data in support of certification applications for October 13, 2016. Laboratories with an expiration date before July 13, 2016 may request the Commission to extend their expiration date to July 13, 2016.

(f) Measurement facilities used to make radiated emission measurements from 1 GHz to 40 GHz shall comply with the site validation option of ANSI C63.4-2014, (clause 5.5.1a)1)) which references CISPR 16-1-4:2010-04 (incorporated by reference, see Sec. 2.910) by July 13, 2018.

(g) Measurements for intentional radiators subject to part 15 of this chapter are to be made using the procedures in ANSI C63.10-2013 (incorporated by reference, see Sec. 2.910) by July 13, 2016.

(h) Measurements for unintentional radiators are to be made using the procedures in ANSI C63.4, except clauses 4.5.3, 4.6, 6.2.13, 8.2.2, 9, and 13 (incorporated by reference, see Sec. 2.910), by July 13, 2016. [80 FR 33443, June 12, 2015]

Verification

Authority: Sections 2.951 through 2.957 are issued under secs. 4, 303, 307, 48 Stat., as amended, 1066, 1082, 1083; 47 U.S.C. 154, 303, 307.

Source: Sections 2.951 through 2.957 appear at 46 FR 23249, Apr. 24, 1981, unless otherwise noted.