CFR /  Title 48  /  Part 211  /  211.503 Contract clauses.

(b) Use the clause at FAR 52.211-12, Liquidated Damages--Construction, in all construction contracts exceeding $700,000, except cost-plus-fixed-fee contracts or contracts where the contractor cannot control the pace of the work. Use of the clause in contracts of $700,000 or less is optional. [60 FR 61594, Nov. 30, 1995. Redesignated at 66 FR 49861, Oct. 1, 2001; 71 FR 75892, Dec. 19, 2006; 75 FR 45073, Aug. 2, 2010; 80 FR 36904, June 26, 2015]