CFR /  Title 48  /  Part 232  /  232.1001 Policy.

(a) As with all contract financing, the purpose of performance-based payments is to assist the contractor in the payment of costs incurred during the performance of the contract. Therefore, performance-based payments should never exceed total cost incurred at any point during the contract. See PGI 232.1001(a) for additional information on use of performance-based payments.

(d) The contracting officer shall use the following standard payment terms for performance-based payments: The contractor entitlement date, if any, specified in the contract, or 14 days after receipt by the designated billing office of a proper request for payment, whichever is later. [63 FR 11537, Mar. 9, 1998, as amended at 79 FR 17936, Mar. 31, 2014]