Code of Federal Regulations (alpha)

CFR /  Title 48  /  Part 342  /  342.7003-1 Solicitation provisions and contract clauses.

(a) The Contracting Officer shall insert the clause in 352.242-73, Withholding of Contract Payments, and the clause in FAR 52.249-14, Excusable Delays, in solicitations and contracts when a cost-reimbursement, time-and-materials, or labor-hour contract is contemplated.

(b) The Contracting Officer shall insert the clause in 352.242-74, Final Decisions on Audit Findings, in solicitations and contracts when a cost-reimbursement contract is contemplated, except for those contracts with:

(1) A foreign government or agency of that government; or

(2) An international organization or a subsidiary body of that organization that the HCA determines would not be appropriate.