Code of Federal Regulations (alpha)

CFR /  Title 49  /  Part 192  /  Sec. 192.112 Additional design requirements for steel pipe using

For a new or existing pipeline segment to be eligible for operation at the alternative maximum allowable operating pressure (MAOP) calculated under Sec. 192.620, a segment must meet the following additional design requirements. Records for alternative MAOP must be maintained, for the useful life of the pipeline, demonstrating compliance with these requirements: ------------------------------------------------------------------------

The pipeline segment must meet these

(a) General standards for the (1) The plate, skelp, or coil used

steel pipe. for the pipe must be micro-alloyed,

fine grain, fully killed,

continuously cast steel with

calcium treatment.

(2) The carbon equivalents of the

steel used for pipe must not exceed

0.25 percent by weight, as

calculated by the Ito-Bessyo

formula (Pcm formula) or 0.43

percent by weight, as calculated by

the International Institute of

Welding (IIW) formula.

(3) The ratio of the specified

outside diameter of the pipe to the

specified wall thickness must be

less than 100. The wall thickness

or other mitigative measures must

prevent denting and ovality

anomalies during construction,

strength testing and anticipated

operational stresses.

(4) The pipe must be manufactured

using API Spec 5L, product

specification level 2 (incorporated

by reference, see Sec. 192.7) for

maximum operating pressures and

minimum and maximum operating

temperatures and other requirements

(1) The toughness properties for

pipe must address the potential for

initiation, propagation and arrest

of fractures in accordance with:

(i) API Spec 5L (incorporated by

reference, see Sec. 192.7); or

(ii) American Society of Mechanical

Engineers (ASME) B31.8

(incorporated by reference, see

Sec. 192.7); and

(iii) Any correction factors needed

to address pipe grades, pressures,

temperatures, or gas compositions

not expressly addressed in API Spec

5L , product specification level 2

or ASME B31.8 (incorporated by

reference, see Sec. 192.7).

(2) Fracture control must:

(i) Ensure resistance to fracture

initiation while addressing the

full range of operating

temperatures, pressures, gas

compositions, pipe grade and

operating stress levels, including

maximum pressures and minimum

temperatures for shut-in

conditions, that the pipeline is

expected to experience. If these

parameters change during operation

of the pipeline such that they are

outside the bounds of what was

considered in the design

evaluation, the evaluation must be

reviewed and updated to assure

continued resistance to fracture

initiation over the operating life

of the pipeline;

(ii) Address adjustments to

toughness of pipe for each grade

used and the decompression behavior

of the gas at operating parameters;

(iii) Ensure at least 99 percent

probability of fracture arrest

within eight pipe lengths with a

probability of not less than 90

percent within five pipe lengths;

and

(iv) Include fracture toughness

testing that is equivalent to that

described in supplementary

requirements SR5A, SR5B, and SR6 of

API Specification 5L (incorporated

by reference, see Sec. 192.7) and

ensures ductile fracture and arrest

with the following exceptions:

(A) The results of the Charpy impact

test prescribed in SR5A must

indicate at least 80 percent

minimum shear area for any single

test on each heat of steel; and

(B) The results of the drop weight

test prescribed in SR6 must

indicate 80 percent average shear

area with a minimum single test

result of 60 percent shear area for

any steel test samples. The test

results must ensure a ductile

fracture and arrest.

(3) If it is not physically possible

to achieve the pipeline toughness

properties of paragraphs (b)(1) and

(2) of this section, additional

design features, such as mechanical

or composite crack arrestors and/or

heavier walled pipe of proper

design and spacing, must be used to

ensure fracture arrest as described

in paragraph (b)(2)(iii) of this

(1) There must be an internal

quality management program at all

mills involved in producing steel,

plate, coil, skelp, and/or rolling

pipe to be operated at alternative

MAOP. These programs must be

structured to eliminate or detect

defects and inclusions affecting

pipe quality.

(2) A mill inspection program or

internal quality management program

must include (i) and either (ii) or

(iii):

(i) An ultrasonic test of the ends

and at least 35 percent of the

surface of the plate/coil or pipe

to identify imperfections that

impair serviceability such as

laminations, cracks, and

inclusions. At least 95 percent of

the lengths of pipe manufactured

must be tested. For all pipelines

designed after December 22, 2008,

the test must be done in accordance

with ASTM A578/A578M Level B, or

API Spec 5L Paragraph 7.8.10

(incorporated by reference, see

Sec. 192.7) or equivalent method,

and either

(ii) A macro etch test or other

equivalent method to identify

inclusions that may form centerline

segregation during the continuous

casting process. Use of sulfur

prints is not an equivalent method.

The test must be carried out on the

first or second slab of each

sequence graded with an acceptance

criteria of one or two on the

Mannesmann scale or equivalent; or

(iii) A quality assurance monitoring

program implemented by the operator

that includes audits of: (a) all

steelmaking and casting facilities,

(b) quality control plans and

manufacturing procedure

specifications, (c) equipment

maintenance and records of

conformance, (d) applicable casting

superheat and speeds, and (e)

centerline segregation monitoring

records to ensure mitigation of

centerline segregation during the

(1) There must be a quality

assurance program for pipe seam

welds to assure tensile strength

provided in API Spec 5L

(incorporated by reference, see

Sec. 192.7) for appropriate

grades.

(2) There must be a hardness test,

using Vickers (Hv10) hardness test

method or equivalent test method,

to assure a maximum hardness of 280

Vickers of the following:

(i) A cross section of the weld seam

of one pipe from each heat plus one

pipe from each welding line per

day; and

(ii) For each sample cross section,

a minimum of 13 readings (three for

each heat affected zone, three in

the weld metal, and two in each

section of pipe base metal).

(3) All of the seams must be

ultrasonically tested after cold

expansion and mill hydrostatic

(1) All pipe to be used in a new

pipeline segment installed after

October 1, 2015, must be

hydrostatically tested at the mill

at a test pressure corresponding to

a hoop stress of 95 percent SMYS

for 10 seconds.

(2) Pipe in operation prior to

December 22, 2008, must have been

hydrostatically tested at the mill

at a test pressure corresponding to

a hoop stress of 90 percent SMYS

for 10 seconds.

(3) Pipe in operation on or after

December 22, 2008, but before

October 1, 2015, must have been

hydrostatically tested at the mill

at a test pressure corresponding to

a hoop stress of 95 percent SMYS

for 10 seconds. The test pressure

may include a combination of

internal test pressure and the

allowance for end loading stresses

imposed by the pipe mill

hydrostatic testing equipment as

allowed by ``ANSI/API Spec 5L''

(incorporated by reference, see

(1) The pipe must be protected

against external corrosion by a non-

shielding coating.

(2) Coating on pipe used for

trenchless installation must be non-

shielding and resist abrasions and

other damage possible during

installation.

(3) A quality assurance inspection

and testing program for the coating

must cover the surface quality of

the bare pipe, surface cleanliness

and chlorides, blast cleaning,

application temperature control,

adhesion, cathodic disbondment,

moisture permeation, bending,

coating thickness, holiday

(1) There must be certification

records of flanges, factory

induction bends and factory weld

ells. Certification must address

material properties such as

chemistry, minimum yield strength

and minimum wall thickness to meet

design conditions.

(2) If the carbon equivalents of

flanges, bends and ells are greater

than 0.42 percent by weight, the

qualified welding procedures must

include a pre-heat procedure.

(3) Valves, flanges and fittings

must be rated based upon the

required specification rating class

(1) A compressor station must be

designed to limit the temperature

of the nearest downstream segment

operating at alternative MAOP to a

maximum of 120 degrees Fahrenheit

(49 degrees Celsius) or the higher

temperature allowed in paragraph

(h)(2) of this section unless a

(2) of this section unless a

long-term coating integrity

monitoring program is implemented

in accordance with paragraph (h)(3)

of this section.

(2) If research, testing and field

monitoring tests demonstrate that

the coating type being used will

withstand a higher temperature in

long-term operations, the

compressor station may be designed

to limit downstream piping to that

higher temperature. Test results

and acceptance criteria addressing

coating adhesion, cathodic

disbondment, and coating condition

must be provided to each PHMSA

pipeline safety regional office

where the pipeline is in service at

least 60 days prior to operating

above 120 degrees Fahrenheit (49

degrees Celsius). An operator must

also notify a State pipeline safety

authority when the pipeline is

located in a State where PHMSA has

an interstate agent agreement, or

an intrastate pipeline is regulated

by that State.

(3) Pipeline segments operating at

alternative MAOP may operate at

temperatures above 120 degrees

Fahrenheit (49 degrees Celsius) if

the operator implements a long-term

coating integrity monitoring

program. The monitoring program

must include examinations using

direct current voltage gradient

(DCVG), alternating current voltage

gradient (ACVG), or an equivalent

method of monitoring coating

integrity. An operator must specify

the periodicity at which these

examinations occur and criteria for

repairing identified indications.

An operator must submit its long-

term coating integrity monitoring

program to each PHMSA pipeline

safety regional office in which the

pipeline is located for review

before the pipeline segments may be

operated at temperatures in excess

of 120 degrees Fahrenheit (49

degrees Celsius). An operator must

also notify a State pipeline safety

authority when the pipeline is

located in a State where PHMSA has

an interstate agent agreement, or

an intrastate pipeline is regulated

by that State.------------------------------------------------------------------------ [73 FR 62175, Oct. 17, 2008, as amended by Amdt. 192-111, 74 FR 62505, Nov. 30, 2009; Amdt. 192-119, 80 FR 180, Jan. 5, 2015; Amdt. 192-120, 80 FR 12777, Mar. 11, 2015]