(a) The participant and NRCS may modify a contract if both parties agree to the contract modification, the contract continues to meet the purposes of the program, and the contract modification is approved by NRCS.

(b) It is the participant's responsibility to notify NRCS when the participant anticipates either the voluntary or involuntary loss of control of the land covered by an EQIP contract.

(c) The participant and NRCS may agree to transfer a contract to another party.

(1) To receive an EQIP payment, the transferee must be determined by NRCS to be eligible to participate in EQIP and must assume full responsibility under the contract, including the O&M; agreement for those conservation practices already installed and those conservation practices to be installed as a condition of the contract.

(2) If the transferee is ineligible or refuses to accept future payments, NRCS will terminate the contract and may require the transferor to refund or forfeit all payments received.

(d) NRCS may require a participant to refund all or a portion of any financial assistance provided under EQIP if the participant sells or loses control of the land covered by an EQIP contract and the new owner or controller is not eligible to participate in the program or refuses to assume responsibility under the contract.

(e) In the event a conservation practice fails through no fault of the participant, NRCS may issue payments to re-establish the practice, at the rates established in accordance with Sec. 1466.23, provided such payments do not exceed the payment limitation requirements as set forth Sec. 1466.24.