(a) Preapplications. (1) The preapplication package must be submitted either alone or the necessary information may be submitted simultaneously with the application. The preapplication package will contain:

(1) The preapplication package must be submitted either alone or the necessary information may be submitted simultaneously with the application. The preapplication package will contain:

(i) An Application for Federal Assistance on a form provided by the Agency (available in any Agency office);

(ii) State intergovernmental or other type review comments and recommendations for the borrower's project (clearinghouse comments, if applicable);

(iii) Supporting documentation necessary to make an eligibility determination such as financial statements, audits, copies of organizational documents, existing debt instruments, etc.; and

(iv) Documentation of lender eligibility in accordance with Sec. 3575.27.

(2) If the Agency determines that the project may meet requirements and is likely to be funded, the lender must submit a complete application if it has not previously submitted one. The Agency must do an environmental review before further processing will be completed.

(b) Applications. Contents of application package:

(1) Application for Loan and Guarantee on a form prescribed by the Agency (available in any Agency office);

(2) Proposed loan agreement;

(3) Request for Environmental Information (available in any Agency office);

(4) Preliminary architectural or engineering report;

(5) Cost estimates;

(6) Appraisal reports (as appropriate);

(7) Credit reports;

(8) Financial feasibility analysis and report; and

(9) Any additional information required.