The Committee's role is to provide input and recommendations to BIA and FHWA regarding:

(a) New IRR Inventory Data Format and Form;

(b) Simplified Cost to Construct (CTC) Methodology (including formula calculations, formula program and design, and bid tab methodology);

(c) Cost Elements;

(d) Over-Design Issues;

(e) Inflation Impacts on $1 Million Cap for IRRHPP and Emergency Projects (including the IRRHPP Ranking System and emergency/disaster expenditures report); and

(f) The impact of including funded but non-constructed projects in the CTC calculation.