Code of Federal Regulations (alpha)

CFR /  Title 30  /  Part 585  /  Sec. 585.235 If I have a commercial lease, how long will my lease

(a) For commercial leases, the lease terms and applicable automatic extensions are as shown in the following table: ------------------------------------------------------------------------

(1) Each commercial lease If BOEM receives a The SAP must meet

will have a preliminary SAP that satisfies the requirements of

term of 12 months, within the requirements of Sec. Sec.

which the lessee must Sec. Sec. 585.605 through

submit: (i) a SAP; or (ii) 585.605 through 585.613. The SAP/

a combined SAP and 585.613 or a SAP/ COP must meet the

Construction and Operations COP that satisfies requirements of

Plan (COP). The preliminary the requirements of Sec. Sec.

term begins on the Sec. Sec. 585.605 through

effective date of the lease. 585.605 through 585.613 and Sec.

585.613 and Sec. Sec. 585.620

Sec. 585.620 through 585.629.

through 585.629,

the preliminary

term will be

extended for the

time necessary for

us to conduct

technical and

environmental

reviews of the SAP

or SAP/COP.(2) A commercial lease will If we receive a COP The COP must meet

have a site assessment term that satisfies the the requirements of

of five years to conduct requirements of Sec. Sec.

site assessment activities Sec. Sec. 585.620 through

and to submit a COP, if a 585.620 through 585.629 of this

SAP/COP has not been 585.629, the site part.

submitted. Your site assessment term

assessment term begins when will be

BOEM approves your SAP or automatically

SAP/COP. extended for the

period of time

necessary for us to

conduct technical

and environmental

reviews of the COP.(3) A commercial lease will .................... The lease renewal

have an operations term of request must meet

25 years, unless a longer the requirements in

term is negotiated by the Sec. Sec.

parties. A request for 585.425 through

lease renewal must be 585.429.

submitted two years before

the end of the operations

term. If you submit a COP,

your operations term begins

on the date that BOEM

approves the COP. If you

submit a SAP/COP, your

operations term begins on

the earliest of the

following dates: five years

after BOEM approves the SAP/

COP; when fabrication

begins; or, when

installation commences.(4) A commercial lease may .................... NOTE: BOEM may also

have additional time added order or grant a

to the operations term suspension of the

through a lease renewal. operations term, as

The term of the lease provided in Sec.

renewal will not exceed the Sec. 585.415

original term of the lease, through 585.421

unless a longer term is thereby effectively

negotiated by the parties. extending the term

The lease renewal term of the lease.

begins upon expiration of

the original operations

term.------------------------------------------------------------------------

(b) If you do not timely submit a SAP, COP, or SAP/COP, as appropriate, you may request additional time to extend the preliminary or site assessment term of your commercial lease that includes a revised schedule for submission of the plan, as appropriate. [76 FR 64623, Oct. 18, 2011, as amended at 79 FR 21622, Apr. 17, 2014]