CFR /  Title 30  /  Part 585  /  Sec. 585.600 What plans and information must I submit to BOEM before I conduct

You must submit a SAP, COP, or GAP and receive BOEM approval as set forth in the following table: ------------------------------------------------------------------------

(a) conduct any site assessment activities submit and obtain approval

on your commercial lease, for your SAP according to

Sec. Sec. 585.605

through 585.613.(b) conduct any activities pertaining to submit and obtain approval

construction of facilities for commercial for your COP, according to

operations on your commercial lease, Sec. Sec. 585.620

through 585.629.(c) conduct any activities on your limited submit and obtain approval

lease, ROW grant, or RUE grant in any OCS for your GAP according to

area, Sec. Sec. 585.640

through 585.648.------------------------------------------------------------------------