The District Commander must be notified of the following: ------------------------------------------------------------------------
The District Commander must be
(a) Construction of a pipeline, At least 30 days before
platform, or single point mooring construction begins.
(SPM) is planned.(b) Construction of a pipeline, Within 24 hours, from the date
platform, or SPM begins. construction begins, that the
lights and sound signals are
in use at the construction
site.(c) A light or sound signal is changed Within 24 hours of the change.
during construction.(d) Lights or sound signals used during Within 24 hours of replacement.
construction of a platform, buoy, or
SPM are replaced by permanent fixtures
to meet the requirements of this part.(e) The first cargo transfer operation At least 60 days before the