(a) For non-Federal works undertaken prior to 17 November 1986, credit determinations (deferred until these guidelines became effective) will be made by the Secretary in response to the applications received prior to 31 March 1987. Future non-Federal works for which credit may be allowed under the provisions of section 104 of Pub. L. 99-662 are limited, basically, to local works undertaken while Federal preauthorizations studies of a Federal project for the locality are in progress. Credit consideration for such works will be governed by the procedures set forth here. Non-Federal entities desiring credit should confer with the District Engineer and submit a written application to him. The application will include a full description of planned work, plans, sketches, and similar engineering data and information sufficient to permit analysis of the local proposal.
(b) The District Engineer shall review the engineering adequacy of the local proposal and its relation to the Federal Plan and determine what part of the proposed local improvement would be eligible for credit. The District Engineer will forward his recommendations through the Division Engineer and the Chief of Engineers to the Assistant Secretary of the Army (Civil Works) and provide information on:
(1) Basis for concluding the local plan is appropriate in relation to the prospective Federal plan.
(2) Total estimated cost and benefits of creditable work.
(3) Environmental effects of the local work, including a brief statement of both beneficial and detrimental effects to significant resources.
(4) The urgency for proceeding with the local plan.
(c) Upon being informed of the Secretary's decision, the District Engineer shall reply by letter stating to the local applicant what local work and costs can reasonably be expected to be recommended for credit under the provisions of section 104 (assuming that the final plan for a Federal project, when it is ultimately recommended, remains such as to preserve the local work as a relevant element). If the improvement proposed by the non-Federal entity includes work that will not become a part of the Federal project, the means of determining the part eligible for credit shall be fully defined. This letter shall include the following conditions:
(1) This shall not be interpreted as a Federal assurance regarding later approval of any project nor shall it commit the United States to any type of reimbursement if a Federal project is not undertaken.
(2) This does not eliminate the need for compliance with other Federal, State, and local requirements, including any requirements for permits, Environmental Impact Statements, etc.
(3) Upon authorization of the Federal project, approval shall be subject to rescission if the non-Federal work has not commenced and, as a consequence, Corps planning for orderly implementation of the project is being adversely affected.
(d) The non-Federal entity will notify the District engineer when work commences. The District Engineer will conduct periodic and final inspections. Upon completion of local work, local interests shall provide the District Engineer details of the work accomplished and the actual costs directly associated therewith. The District Engineer shall audit claimed costs to ascertain and confirm those costs properly creditable and shall inform the non-Federal entity of the audit results.
(e) During further Corps studies, the local work actually accomplished that would constitute a legitimate part of the overall recommended Federal project may be incorporated within any plan later recommended for implementation.
(f) The District Engineer shall submit a copy of his letter and notification of creditable costs of completed work to the Secretary through the Division Engineer and the Chief of Engineers.
(g) All justification sheets supporting new start recommendations for Preconstruction Engineering and Design or Construction of projects will include information on credits in the paragraph on local cooperation. The information should include but not be limited to date of the District Engineer's letter to the sponsor pursuant to Sec. 240.9(c) of this regulation, status of the creditable work, estimated or actual cost of the work and the estimated amount of credit.
Sec. Appendix A to Part 240 [Reserved]
Sec. Appendix B to Part 240--Formulas for Determining Amount of
Allowable Credit
1. General. The amount of credit that non-Federal interests may receive under the provisions of section 104 of the Water Resources Development Act of 1986 depends first on the value of the compatible work they have accomplished and then on the value of the local cooperation against which they may receive credit. If the compatible work is for construction which was outside the scope of the project as authorized, the costs for the compatible work for which credit is desired are additive to the original estimate of total project cost. This increases the estimated cost of basic local cooperation requirements, thus enlarging the target against which credit may be given.
2. The ``formulas'' for determining the amount of credit that may be allowed in the various cases are provided in the following paragraphs. TPC means the total estimate of project costs for the project as it was authorized. LERRD means the costs for lands, easements, rights-of-way, relocations and disposal areas as included in that estimate.
3. Calculations for several hypothetical examples are provided to illustrate how crediting determinations would impact on project costs and on cost sharing. For each of these examples it is assumed that the estimated total project cost (TPC) of the project as authorized is $100.0 million. All of the elements of cost are given in millions of dollars.
4. Integral Work. For compatible work that is integral with the project as authorized (240.7(a)(1)) or compatible work that constitutes an advantageous substitution for work integral with the authorized project (i.e., substitute work, 240.7(a)(3)): a. LERRD 420% TPC
Credit = Value of compatible work up to 20% TPCb. LERRD "20% TPC
Credit = Value of compatible work up to LERRD
Crediting non-Federal interests for constructing an integral part of the project or substitute work will not result in any increase in project costs. Ordinarily, the result will simply be a transfer of equivalent responsibilities between the Corps and non-Federal interests. If non-Federal interests should accomplish compatible integral or substitute work exceeding the possible credit, the Corps will be relieved of the expense of constructing an increment of the project. An example is provided below. In this example, non-Federal interests have accomplished integral project work amounting to 30.0 million. LERRD are less than 20% of TPC so that the maximum value of local cooperation against which they may receive credit is $20.0 million. Since the $10.0 for which credit cannot be given nonetheless represents useful project work, in this example the Corps would be relieved of the costs for accomplishing that much construction. ------------------------------------------------------------------------
Credit
Basic Example 1:
Case: LERRD 420% TPC project Compatible
work, 30.0------------------------------------------------------------------------Non-Federal:
5% Cash........................................ 5.0 5.0
LERRD.......................................... 14.0 0.0
Extra cash (toward constr.).................... 6.0 0.0
Construction (actual).......................... ........ 30.0
----------------------
Subtotal................................... 25.0 35.0
======================Federal:
Construction................................... 75.0 51.0
LERRD.......................................... ........ 14.0
----------------------
Subtotal................................... 75.0 65.0
======================
TPC........................................ 100.0 100.0Reduction in Federal costs....................... ........ \1\ 10.0------------------------------------------------------------------------\1\ The amount by which the integral or substitute work actually
accomplished by non-Federal interests exceeds the requirements of
local cooperation against which credit may be given.
5. External Work. For compatible work outside the scope of the project as authorized (i.e., external work, 240.7(a)(2)):a. LERRD 425% TPC
Credit = Value of compatible work up to 25% TPCb. LERRD "25% TPC
Credit = Value of compatible work up to LERRD
Crediting non-Federal interests for compatible work which was not part of the project as authorized (external work) will result in an increase in project costs and an increase in the net Federal costs. The costs for compatible external work for which non-Federal interests desire credit must be incorporated into the estimate of total project costs (but only to the extent that credit can actually be given). Assigned Federal and non-Federal project costs then making up the adjusted total project costs will both be greater than for the basic project. However, the net effect will be a savings to non-Federal interests in the further costs they will have for fulfilling local cooperation requirements. The maximum amount that can be credited for compatible external work (and thus added to project costs), where LERRD 425% TPC, follows from Credit, C = 20% (TPC + C) which reduces to C = 0.2TPC + 0.2C, then to 0.8C = 0.2TPC, and finally C = (0.2/0.8)TPC or 0.25TPC as indicated in a, above. An example of crediting in a case involving external work is provided below. In this example, as in example 1, non-Federal interests have accomplished work amounting to $30.0 million. This work, however, was not intergral with the project as authorized (it has been determined to be compatible external work), so that any part of it for which credit is given must be added to TPC. Since, in this case LERRD are less than 25% of TPC, the maximum amount that can be credited is 25% of TPC, or $25.0 million. Adjusting TPC by this amount results in an added Federal cost of $18.75 million (75% of the $25.0 million increase). ------------------------------------------------------------------------
Credit
Basic Example 2,
Case: LERRD 425% TPC project Compatible
work, 30.0------------------------------------------------------------------------Non-Federal:
5% Cash....................................... 5.0 6.25
LERRD......................................... 14.0 0.0
Extra cash (toward constr.)................... 6.0 0.0
Construction (actual)......................... ........ 25.0
-----------------------
Subtotal.................................. 25.0 31.25
=======================Federal:
Construction.................................. 75.0 79.75
LERRD......................................... ........ 14.0
-----------------------
Subtotal.................................. 75.0 93.75TPC............................................. 100.0 ............Adjusted TPC.................................... ........ 125.0Excess of Compatible Work....................... ........ \1\ 5.0
Increase in Federal Costs....................... ........ \2\ 18.75------------------------------------------------------------------------\1\ This portion of the compatible external work is not incorporated in
the project costs because it would be a disadvantage to the project
sponsor to do so (if included, the sponsor would become obligated for
an additional 5% up-front cash contribution but without any savings in
other local cooperation because there would be nothing left to give
credit against).\2\ This is also the measure of the net savings to non-Federal interests
by virtue of crediting.
6. Combined integral and external works. For cases where non-Federal interests have accomplished compatible work, some of which is integral with the project as authorized and some of which is outside the original scope (external), determination of the allowable credit is a two step process. Work that is integral to the project is credited first. This, C1, is accomplished in accordance with paragraph 4 above. If, after this step, there remain local cooperation requirements against which credit may be given, credit for compatible external work, C2, is determinable on the following basis. a. LERRD 420% (TPC+C2)
C2=Value of compatible work up to 25% TPC-1.25C1b. LERRD "20% (TPC+C2)
C2=Value of compatible work up to remaining LERRD
Note that total credit, C=C1+C2. Formula 6.a. is derived from C=C1+C2=20% (TPC+C2). An example of crediting in a case involving both kinds of compatible works is provided below. In this example non-Federal interests have accomplished $25.0 million in compatible work, $5.0 of which was integral with the project as authorized and $20.0 of which was external. The integral work is credited in the first step against the extra cash component of the original local cooperation requirements. TPC is unaffected; however, the target against which credit for the external work might be credited has been partially used up. The second step shows only the incremental effects of crediting external work. Using 6.a. the maximum credit that can be given for this work is $18.75 million. Although other non-Federal requirements are extinguished as a result of the credit for the external work, the non-Federal 5% cash contribution increases by $0.9375 million, say $0.94 (5% of $18.75). In the final step, the incremental effects of crediting the external work are added in with the values obtained in step 1. ----------------------------------------------------------------------------------------------------------------
Credit Example 3: Compatible work,\1\
Basic 25.0
Case: LERRD 420% (TPC+C2) project ----------------------------------------
Step 1 Step 2 Final----------------------------------------------------------------------------------------------------------------Non-Federal:
5% Cash............................................... 5.0 5.0 0.94 5.94
LERRD................................................. 14.0 14.0 0.0 0.0
Extra cash (toward constr.)........................... 6.0 1.0 0.0 0.0
Construction (actual)................................. ........... 5.0 18.75 23.75
-----------------------------------------------------
Subtotal............................................ 25.0 25.0 ............ 29.69
=====================================================Federal:
Construction............................................ 75.0 75.0 0.06 75.06
LERRD................................................... ........... ........... 14.0 14.0
-----------------------------------------------------
Subtotal............................................ 75.0 75.0 ............ 89.06TPC....................................................... 100.0 100.0 ............ ............Adjusted TPC.............................................. ........... ........... ............ 118.75Excess of Compatible Worth................................ ........... ........... 1.25 1.25Increase in Federal Costs................................. ........... ........... ............ 14.06----------------------------------------------------------------------------------------------------------------\1\ Compatible work consisting of 5.0 integral work credited in first step of calculations plus 20.0 external
work credited, to the extent possible, in second step.