(a) The requirements of subpart U of this part constitute national primary drinking water regulations. The regulations in this subpart establish monitoring and other requirements for identifying subpart V compliance monitoring locations for determining compliance with maximum contaminant levels for total trihalomethanes (TTHM) and haloacetic acids (five)(HAA5). You must use an Initial Distribution System Evaluation (IDSE) to determine locations with representative high TTHM and HAA5 concentrations throughout your distribution system. IDSEs are used in conjunction with, but separate from, subpart L compliance monitoring, to identify and select subpart V compliance monitoring locations.

(b) Applicability. You are subject to these requirements if your system is a community water system that uses a primary or residual disinfectant other than ultraviolet light or delivers water that has been treated with a primary or residual disinfectant other than ultraviolet light; or if your system is a nontransient noncommunity water system that serves at least 10,000 people and uses a primary or residual disinfectant other than ultraviolet light or delivers water that has been treated with a primary or residual disinfectant other than ultraviolet light.

(c) Schedule. (1) You must comply with the requirements of this subpart on the schedule in the table in this paragraph (c)(1). ----------------------------------------------------------------------------------------------------------------

You must submit your

standard monitoring plan

or system specific study You must complete your

plan \1\ or 40/30 standard monitoring or You must submit your

If you serve this population certification \2\ to the system specific study IDSE report to the

State by or receive very by State by \3\

small system waiver from

State----------------------------------------------------------------------------------------------------------------Systems that are not part of a combined distribution system and systems that serve the largest population in the

(i) =100,000............. October 1, 2006......... September 30, 2008..... January 1, 2009.(ii) 50,000-99,999.................. April 1, 2007........... March 31, 2009......... July 1, 2009.(iii) 10,000-49,999................. October 1, 2007......... September 30, 2009..... January 1, 2010.(iv) <10,000 (CWS Only)............. April 1, 2008........... March 31, 2010......... July 1, 2010.----------------------------------------------------------------------------------------------------------------

Other systems that are part of a combined distribution system----------------------------------------------------------------------------------------------------------------(v) Wholesale system or consecutive --at the same time as --at the same time as --at the same time as

system. the system with the the system with the the system with the

earliest compliance earliest compliance earliest compliance

date in the combined date in the combined date in the combined

distribution system. distribution system. distribution system.----------------------------------------------------------------------------------------------------------------\1\ If, within 12 months after the date identified in this column, the State does not approve your plan or

notify you that it has not yet completed its review, you may consider the plan that you submitted as approved.

You must implement that plan and you must complete standard monitoring or a system specific study no later

than the date identified in the third column.\2\ You must submit your 40/30 certification under Sec. 141.603 by the date indicated.\3\ If, within three months after the date identified in this column (nine months after the date identified in

this column if you must comply on the schedule in paragraph (c)(1)(iii) of this section), the State does not

approve your IDSE report or notify you that it has not yet completed its review, you may consider the report

that you submitted as approved and you must implement the recommended subpart V monitoring as required.

(2) For the purpose of the schedule in paragraph (c)(1) of this section, the State may determine that the combined distribution system does not include certain consecutive systems based on factors such as receiving water from a wholesale system only on an emergency basis or receiving only a small percentage and small volume of water from a wholesale system. The State may also determine that the combined distribution system does not include certain wholesale systems based on factors such as delivering water to a consecutive system only on an emergency basis or delivering only a small percentage and small volume of water to a consecutive system.

(d) You must conduct standard monitoring that meets the requirements in Sec. 141.601, or a system specific study that meets the requirements in Sec. 141.602, or certify to the State that you meet 40/30 certification criteria under Sec. 141.603, or qualify for a very small system waiver under Sec. 141.604.

(1) You must have taken the full complement of routine TTHM and HAA5 compliance samples required of a system with your population and source water under subpart L of this part (or you must have taken the full complement of reduced TTHM and HAA5 compliance samples required of a system with your population and source water under subpart L if you meet reduced monitoring criteria under subpart L of this part) during the period specified in Sec. 141.603(a) to meet the 40/30 certification criteria in Sec. 141.603. You must have taken TTHM and HAA5 samples under Sec. Sec. 141.131 and 141.132 to be eligible for the very small system waiver in Sec. 141.604.

(2) If you have not taken the required samples, you must conduct standard monitoring that meets the requirements in Sec. 141.601, or a system specific study that meets the requirements in Sec. 141.602.

(e) You must use only the analytical methods specified in Sec. 141.131, or otherwise approved by EPA for monitoring under this subpart, to demonstrate compliance with the requirements of this subpart.

(f) IDSE results will not be used for the purpose of determining compliance with MCLs in Sec. 141.64.