Code of Federal Regulations (alpha)

CFR /  Title 40  /  Part 62  /  Sec. 62.14356 Compliance schedules and increments of progress.

(a) Increments of progress. The owner or operator of a designated facility that has a design capacity equal to or greater than 2.5 million megagrams and 2.5 million cubic meters and a nonmethane organic compound emission rate greater than or equal to 50 megagrams per year must achieve the increments of progress specified in paragraphs (a)(1) through (a)(5) of this section to install air pollution control devices to meet the emission standards specified in Sec. 62.14353(b) of this subpart. (Refer to Sec. 62.14351 for a definition of each increment of progress.)

(1) Submit control plan: Submit a final control plan (collection and control system design plan) according to the requirements of Sec. 62.14353(b) of this subpart and 40 CFR 60.752(b)(2).

(2) Award contract(s): Award contract(s) to initiate on-site construction or initiate on-site installation of emission collection and/or control equipment.

(3) Initiate on-site construction: Initiate on-site construction or initiate on-site installation of emission collection and/or control equipment as described in the EPA-approved final control plan.

(4) Complete on-site construction: Complete on-site construction and installation of emission collection and/or control equipment.

(5) Achieve final compliance: Complete construction in accordance with the design specified in the EPA-approved final control plan and connect the landfill gas collection system and air pollution control equipment such that they are fully operating. The initial performance test must be conducted within 180 days after the date the facility is required to achieve final compliance.

(b) Compliance date. For each designated facility that has a design capacity equal to or greater than 2.5 million megagrams and 2.5 million cubic meters and a nonmethane organic compound emission rate greater than or equal to 50 Mg per year, planning, awarding of contracts, and installation of municipal solid waste landfill air emission collection and control equipment capable of meeting the standards in Sec. 62.14353(b) must be accomplished within 30 months after the date the initial emission rate report (or the annual emission rate report) first shows that the nonmethane organic compounds emission rate equals or exceeds 50 megagrams per year.

(c) Compliance schedules. The owner or operator of a designated facility that has a design capacity equal to or greater than 2.5 million megagrams and 2.5 million cubic meters and a nonmethane organic compound emission rate greater than or equal to 50 megagrams per year must achieve the increments of progress specified in paragraphs (a)(1) through (a)(5) of this section according to the schedule specified in paragraph (c)(1) or (c)(2) of this section, unless a site-specific schedule is approved by EPA.

(1) The owner or operator of a designated facility must achieve the increments of progress according to the schedule in table 3 of this subpart, except for those affected facilities specified in paragraph (c)(2) of this section. Once this subpart becomes effective on January 7, 2000, any designated facility to which this subpart applies will remain subject to the schedule in table 3 if a subsequently approved State or Tribal plan contains a less stringent schedule, (i.e., a schedule that provides more time to comply with increments 1, 4 and/or 5 than does this Federal plan).

(2) The owner or operator of the specified designated facility in table 4 of this subpart must achieve the increments of progress according to the schedule in table 4 of this subpart.

(d) For designated facilities that are subject to the schedule requirements of paragraph (c)(1) of this section, the owner or operator (or the State or Tribal air pollution control authority) may submit to the appropriate EPA Regional Office for approval alternative dates for achieving increments 2 and 3. Sec. Table 1 to Subpart GGG of Part 62--States That Have an Approved and

Effective State Plan \a\ ------------------------------------------------------------------------

Effective date

State plan of state plan

\b\------------------------------------------------------------------------Alabama................................................. 12/07/98Allegheny County, Pennsylvania.......................... 04/16/99Arizona................................................. 11/19/99California.............................................. 11/22/99Colorado................................................ 09/28/98Delaware................................................ 11/16/99Florida................................................. 08/03/99Georgia................................................. 01/12/99Illinois................................................ 01/22/99Iowa.................................................... 06/22/98Kansas.................................................. 05/19/98Kentucky................................................ 06/21/99Louisiana............................................... 10/28/97Maryland................................................ 11/8/99Minnesota............................................... 09/25/98Missouri................................................ 06/23/98Montana................................................. 09/08/98Nashville, Tennessee.................................... 02/16/99Nebraska................................................ 06/23/98Nevada.................................................. 11/19/99New Mexico.............................................. 02/10/98New York................................................ 09/17/99North Dakota............................................ 02/13/98Ohio.................................................... 10/06/98Oklahoma................................................ 05/18/99Oregon.................................................. 08/25/98South Carolina.......................................... 10/25/99South Dakota............................................ 08/02/99Tennessee............................................... 11/29/99

Texas................................................... 08/16/99Utah.................................................... 03/16/98Wyoming................................................. 07/31/98------------------------------------------------------------------------\a\ This table is provided as a matter of convenience and is not

controlling in determining whether a MSW landfill is subject to the

Federal plan. A MSW landfill is subject to this Federal plan if it

commenced construction before May 30, 1991 and has not been modified

or reconstructed on or after that date and is not covered by an

approved and currently effective State or Tribal plan.\b\ The State plan is expected to become effective on the date

indicated. However, if the State plan does not become effective on the

date indicated, the Federal plan applies until the State plan becomes

effective. Sec. Table 2 to Subpart GGG of Part 62--States That Submitted a Negative

Declaration Letter \a\ ------------------------------------------------------------------------

Date of

State, locality, or portion of Indian country negative

declaration------------------------------------------------------------------------District of Columbia.................................... 09/11/97New Hampshire........................................... 07/22/98Philadelphia, Pennsylvania.............................. 02/27/96Rhode Island............................................ 05/27/98Vermont................................................. 08/20/96------------------------------------------------------------------------\a\ A MSW landfill with a design capacity equal to or greater than 2.5

million megagrams and 2.5 million cubic meters located in an area for

which a negative declaration letter was submitted is subject to the

Federal plan, notwithstanding the negative declaration letter and this

table 2.

Table 3 to Subpart GGG of Part 62--Generic Compliance Schedule and

Increments of Progress \a\ ------------------------------------------------------------------------

Increment Date------------------------------------------------------------------------Increment 1--Submit final control plan. 1 year after initial NMOC

emission rate report or the

first annual emission rate

report showing NMOC emissions

=50 Mg/yr.\b\Increment 2--Award Contracts........... 20 months after initial NMOC

emission rate report or the

first annual emission rate

report showing NMOC emissions

=50 Mg/yr.\b\Increment 3--Begin on-site construction 24 months after initial NMOC

emission rate report or the

first annual emission rate

report showing NMOC emissions

=50 Mg/yr.\b\Increment 4--Complete on-site 30 months after initial NMOC

construction. emission rate report or the

first annual emission rate

report showing NMOC emissions

=50 Mg/yr.\b\Increment 5--Final compliance.......... 30 months after initial NMOC

emission rate report or the

first annual emission rate

report showing NMOC emissions

=50 Mg/yr.\b\------------------------------------------------------------------------\a\ Table 3 of subpart GGG applies to landfills with design capacities

=2.5 million megagrams and 2.5 million cubic meters that

are subject to this subpart except those with site-specific compliance

schedules shown in table 4 of subpart GGG.\b\ NMOC = nonmethane organic compounds Mg/yr = megagrams per year

Sec. Table 4 to Subpart GGG of Part 62--Site-Specific Compliance

Schedules and Increments of Progress [Reserved]

Subpart HHH_Federal Plan Requirements for Hospital/Medical/Infectious

Waste Incinerators Constructed On Or Before December 1, 2008

Source: 65 FR 49881, Aug. 15, 2000, unless otherwise noted.

Applicability