(a) Periodic reports. The owner or operator shall report the information specified in paragraphs (a)(1) through (a)(2) of this section, as applicable, in the periodic report specified in the referencing subpart.
(1) The initial Periodic Report shall include the information specified in paragraphs (a)(1)(i) through (a)(1)(iv) and (a)(2) of this section.
(i) Process unit or affected facility identification.
(ii) Number of valves subject to the requirements of Sec. 63.1006, excluding those valves designated for no detectable emissions under the provisions of Sec. 63.1006(e)(4).
(iii) Number of pumps subject to the requirements of Sec. 63.1007, excluding those pumps designated for no detectable emissions under the provisions of Sec. 63.1007(e)(2) and those pumps complying with the closed vent system provisions of Sec. 63.1007(e)(3).
(iv) Number of compressors subject to the requirements of Sec. 63.1012, excluding those compressors designated for no detectable emissions under the provisions of Sec. 63.1012(f) and those compressors complying with the closed vent system provisions of Sec. 63.1012(e).
(2) Each periodic report shall contain the information listed in paragraphs (a)(2)(i) through (a)(2)(iv) of this section, as applicable.
(i) Process unit identification.
(ii) For each month during the semiannual reporting period,
(A) Number of valves for which leaks were detected as described in Sec. 63.1006(b),
(B) Number of valves for which leaks were not repaired as required in Sec. 63.1006(d),
(C) Number of pumps for which leaks were detected as described in Sec. 63.1007(b) and Sec. 63.1007(e)(1)(vi),
(D) Number of pumps for which leaks were not repaired as required in Sec. Sec. 63.1007(d) and (e)(5),
(E) Number of compressors for which leaks were detected as described in Sec. 63.1012(d)(1),
(F) Number of compressors for which leaks were not repaired as required in Sec. 63.1012(d)(1), and
(G) The facts that explain each delay of repair and, where appropriate, why the repair was technically infeasible without a process unit or affected facility shutdown.
(iii) Dates of process unit or affected facility shutdowns which occurred within the periodic report reporting period.
(iv) Revisions to items reported according to paragraph (a)(1) of this section if changes have occurred since the initial report or subsequent revisions to the initial report.
(b) Special notifications. An owner or operator electing to comply with either of the alternatives in Sec. 63.1006(b)(5) or (6) shall notify the Administrator of the alternative standard selected before implementing either of the provisions. Subpart UU_National Emission Standards for Equipment Leaks_Control Level
2 Standards