CFR /  Title 40  /  Part 63  /  Sec. 63.11164 What General Provisions apply to primary zinc production

(a) If you own or operate an existing affected source, you must comply with the requirements of the General Provisions in 40 CFR part 63, subpart A, according to Table 1 to this subpart and paragraphs (a)(1) through (3) of this section.

(1) Your notification of compliance status required by Sec. 63.9(h) must include this certification of compliance, signed by a responsible official, for the work practice standards in Sec. 63.11162(a): ``This facility complies with the work practice standards in Sec. 63.11162(a).''

(2) If you certify compliance with the PM emissions limits in Sec. 63.11162(b) based on a previous performance test, your notification of compliance status required by Sec. 63.9(h) must include this certification of compliance, signed by a responsible official: ``This facility complies with the PM emissions limits in Sec. 63.11162(b) based on a previous performance test.''

(3) If you conduct a new performance test to demonstrate compliance with the PM emissions limits for a furnace in Sec. 63.11162(b), your notification of compliance status required by Sec. 63.9(h) must include the results of the performance test, including required monitoring data.

(b) If you own or operate a new affected source, you must comply with the requirements of the General Provisions (40 CFR part 63, subpart A) as provided in Table 1 to this subpart and paragraphs (b)(1) through (4) of this section.

(1) Your notification of compliance status required in Sec. 63.9(h) must include the results of the initial performance tests, including required monitoring data.

(2) Your notification of compliance status required by Sec. 63.9(h) must include this certification of compliance, signed by a responsible official, for the work practice standard in Sec. 63.11163(a): ``This facility complies with the work practice standards in Sec. 63.11163(a).''

(3) Your notification of compliance status required by Sec. 63.9(h) must include this certification of compliance, signed by a responsible official, for the capture system requirements in Sec. 63.11163(c): ``This facility has installed capture systems according to Sec. 63.11163(c).''

(4) If you use a baghouse that is subject to the requirements in Sec. 63.11163(d), your notification of compliance status required by Sec. 63.9(h) must include this certification of compliance, signed by a responsible official, for the bag leak detection system requirements in Sec. 63.11163(d): ``This facility has an approved monitoring plan in accordance with Sec. 63.11163(d).''

(5) If you use control devices other than baghouses, your notification of compliance status required by Sec. 63.9(h) must include this certification of compliance, signed by a responsible official for the monitoring plan requirements in Sec. 63.11163(i): ``This facility has an approved monitoring plan in accordance with Sec. 63.11163(i).''

Primary Beryllium Production Facilities