Code of Federal Regulations (alpha)

CFR /  Title 40  /  Part 63  /  Sec. 63.611 Implementation and enforcement.

(a) This subpart can be implemented and enforced by the U.S. EPA, or a delegated authority such as the applicable State, local, or Tribal agency. If the U.S. EPA Administrator has delegated authority to a State, local, or Tribal agency, then that agency, in addition to the U.S. EPA, has the authority to implement and enforce this subpart. Contact the applicable U.S. EPA Regional Office to find out if implementation and enforcement of this subpart is delegated to a State, local, or Tribal agency.

(b) In delegating implementation and enforcement authority of this subpart to a State, local, or Tribal agency under subpart E of this part, the authorities contained in paragraph (c) of this section are retained by the Administrator of U.S. EPA and cannot be transferred to the State, local, or Tribal agency.

(c) The authorities that cannot be delegated to State, local, or Tribal agencies are as specified in paragraphs (c)(1) through (4) of this section.

(1) Approval of alternatives to the requirements in Sec. Sec. 63.600, 63.602 through 63.604, and 63.609 through 63.610.

(2) Approval of major alternatives to test methods under Sec. 63.7(e)(2)(ii) and (f), as defined in Sec. 63.90, and as required in this subpart.

(3) Approval of major alternatives to monitoring under Sec. 63.8(f), as defined in Sec. 63.90, and as required in this subpart.

(4) Approval of major alternatives to recordkeeping and reporting under Sec. 63.10(f), as defined in Sec. 63.90, and as required in this subpart. [68 FR 37351, June 23, 2003]

Sec. Appendix A to Subpart AA of Part 63--Applicability of General

Provisions (40 CFR Part 63, Subpart A) to Subpart AA ----------------------------------------------------------------------------------------------------------------

40 CFR citation Requirement Applies to subpart AA Comment----------------------------------------------------------------------------------------------------------------63.1(a)(1) through (4).............. General Applicability.. Yes.63.1(a)(5).......................... ....................... No...................... [Reserved].63.1(a)(6) through (8).............. ....................... Yes.63.1(a)(9).......................... ....................... No...................... [Reserved].63.1(a)(10) through (14)............ ....................... Yes.63.1(b)............................. Initial Applicability Yes.

Determination.63.1(c)(1).......................... Applicability After Yes.

Standard Established.63.1(c)(2).......................... ....................... Yes..................... Some plants may be area

sources.63.1(c)(3).......................... ....................... No...................... [Reserved].63.1(c)(4) and (5).................. ....................... Yes.63.1(d)............................. ....................... No...................... [Reserved].63.1(e)............................. Applicability of Permit Yes.

Program.63.2................................ Definitions............ Yes..................... Additional definitions

in Sec. 63.601.63.3................................ Units and Abbreviations Yes.63.4(a)(1) through (3).............. Prohibited Activities.. Yes.63.4(a)(4).......................... ....................... No...................... [Reserved].63.4(a)(5).......................... ....................... Yes.63.4(b) and (c)..................... Circumvention/ Yes.

Severability.63.5(a)............................. Construction/ Yes.

Reconstruction

Applicability.63.5(b)(1).......................... Existing, New, Yes.

Reconstructed Sources

Requirements.63.5(b)(2).......................... ....................... No...................... [Reserved].63.5(b)(3) through (6).............. ....................... Yes.63.5(c)............................. ....................... No...................... [Reserved].63.5(d)............................. Application for Yes.

Approval of

Construction/

Reconstruction.63.5(e)............................. Approval of Yes.

Construction/

Reconstruction.63.5(f)............................. Approval of Yes.

Construction/

Reconstruction Based

on State Review.63.6(a)............................. Compliance with Yes.

Standards and

Maintenance

Applicability.63.6(b)(1) through (5).............. New and Reconstructed Yes. See also Sec. 63.609.

Sources Dates.63.6(b)(6).......................... ....................... No...................... [Reserved].63.6(b)(7).......................... ....................... Yes.63.6(c)(1).......................... Existing Sources Dates. Yes. Sec. 63.609 specifies

dates.63.6(c)(2).......................... ....................... Yes.63.6(c)(3) and (4).................. ....................... No...................... [Reserved].63.6(c)(5).......................... ....................... Yes.63.6(d)............................. ....................... No...................... [Reserved].63.6(e)(1) and (2).................. Operation & Maintenance Yes

Requirements.63.6(e)(3).......................... Startup, Shutdown, and Yes

Malfunction Plan.

63.6(f)............................. Compliance with Yes

Emission Standards.63.6(g)............................. Alternative Standard... Yes.63.6(h)............................. Compliance with Opacity/ No...................... Subpart AA does not

VE Standards. include VE/opacity

standards.63.6(i)(1) through (14)............. Extension of Compliance Yes.63.6(i)(15)......................... ....................... No...................... [Reserved].63.6(i)(16)......................... ....................... Yes.63.6(j)............................. Exemption from Yes.

Compliance.63.7(a)............................. Performance Test Yes. Sec. 63.609(a)

Requirements applies rather than

Applicability. Sec.

63.7(a)(2)(iii).63.7(b)............................. Notification........... Yes.63.7(c)............................. Quality Assurance/Test Yes.

Plan.63.7(d)............................. Testing Facilities..... Yes.63.7(e)............................. Conduct of Tests....... Yes. Sec. Sec. 63.604 and

63.605 specify

additional

requirements.63.7(f)............................. Alternative Test Method Yes.63.7(g)............................. Data Analysis.......... Yes.63.7(h)............................. Waiver of Tests........ Yes.63.8(a)(1).......................... Monitoring Requirements Yes.

Applicability.63.8(a)(2).......................... ....................... No...................... Subpart AA does not

require CMS

performance

specifications.63.8(a)(3).......................... ....................... No...................... [Reserved].63.8(a)(4).......................... ....................... Yes.63.8(b)............................. Conduct of Monitoring.. Yes.63.8(c)(1) through (4).............. CMS Operation/ Yes.

Maintenance.63.8(c)(5) through (8).............. ....................... No...................... Subpart AA does not

require COMS/CEMS or

CMS performance

specifications.63.8(d)............................. Quality Control........ Yes.63.8(e)............................. CMS Performance No...................... Subpart AA does not

Evaluation. require CMS

performance

evaluations63.8(f)(1) through (5).............. Alternative Monitoring Yes.

Method.63.8(f)(6).......................... Alternative to RATA No...................... Subpart AA does not

Test. require CEMS.63.8(g)(1).......................... Data Reduction......... Yes.63.8(g)(2).......................... ....................... No...................... Subpart AA does not

require COMS or CEMS63.8(g)(3) through (5).............. ....................... Yes.63.9(a)............................. Notification Yes.

Requirements

Applicability.63.9(b)............................. Initial Notifications.. Yes.63.9(c)............................. Request for Compliance Yes.

Extension.63.9(d)............................. New Source Notification Yes.

for Special Compliance

Requirements.63.9(e)............................. Notification of Yes.

Performance Test.63.9(f)............................. Notification of VE/ No...................... Subpart AA does not

Opacity Test. include VE/opacity

standards.63.9(g)............................. Additional CMS No...................... Subpart AA does not

Notifications. require CMS

performance

evaluation, COMS, or

CEMS.63.9(h)(1) through (3).............. Notification of Yes.

Compliance Status.63.9(h)(4).......................... ....................... No...................... [Reserved].63.9(h)(5) and (6).................. ....................... Yes.63.9(i)............................. Adjustment of Deadlines Yes.63.9(j)............................. Change in Previous Yes.

Information.63.10(a)............................ Recordkeeping/Reporting- Yes.

Applicability.63.10(b)............................ General Recordkeeping Yes.

Requirements.63.10(c)(1)......................... Additional CMS Yes.

Recordkeeping.63.10(c)(2) through (4)............. ....................... No...................... [Reserved].63.10(c)(5)......................... ....................... Yes.63.10(c)(6)......................... ....................... No...................... Subpart AA does not

require CMS

performance

specifications.63.10(c)(7) and (8)................. ....................... Yes.63.10(c)(9)......................... ....................... No...................... [Reserved].63.10(c)(10) through (13)........... ....................... Yes.63.10(c)(14)........................ ....................... No...................... Subpart AA does not

require a CMS quality

control program.63.10(c)(15)........................ ....................... Yes.

63.10(d)(1)......................... General Reporting Yes.

Requirements.63.10(d)(2)......................... Performance Test Yes.

Results.63.10(d)(3)......................... Opacity or VE No...................... Subpart AA does not

Observations. include VE/opacity

standards.63.10(d)(4) and (5)................. Progress Reports/ Yes.

Startup, Shutdown, and

Malfunction Reports.63.10(e)(1) and (2)................. Additional CMS Reports. No...................... Subpart AA does not

require CEMS or CMS

performance

evaluations.63.10(e)(3)......................... Excess Emissions/CMS Yes..................... Sec. 63.606(c)(2)

Performance Reports. includes additional

requirements. A CMS

performance report is

not required.63.10(e)(4)......................... COMS Data Reports...... No...................... Subpart AA does not

require COMS.63.10(f)............................ Recordkeeping/Reporting Yes.

Waiver.63.11(a)............................ Control Device Yes.

Requirements

Applicability.63.11(b)............................ Flares................. No...................... Flares not applicable.63.12............................... State Authority and Yes.

Delegations.63.13............................... Addresses.............. Yes.63.14............................... Incorporation by Yes.

Reference.63.15............................... Information Yes.

Availability/

Confidentiality.---------------------------------------------------------------------------------------------------------------- Subpart BB_National Emission Standards for Hazardous Air Pollutants From

Phosphate Fertilizers Production Plants