(a) For a capture system applied to emissions from a sinter plant discharge end or blast furnace casthouse or to secondary emissions from a BOPF, you have demonstrated initial compliance if you meet all of the conditions in paragraphs (a)(1) through (4) of this section.
(1) Prepared the capture system operation and maintenance plan according to the requirements of Sec. 63.7800(b), including monthly inspection procedures and detailed descriptions of the operating parameter(s) selected to monitor the capture system;
(2) Certified in your performance test report that the system operated during the test at the operating limits established in your operation and maintenance plan;
(3) Submitted a notification of compliance status according to the requirements in Sec. 63.7840(e), including a copy of the capture system operation and maintenance plan and your certification that you will operate the capture system at the values or settings established for the operating limits in that plan; and
(4) Prepared a site-specific monitoring plan according to the requirements in Sec. 63.7831(a).
(b) For each control device subject to operating limits in Sec. 63.7790(b)(2) or (3), you have demonstrated initial compliance if you meet all the conditions in paragraphs (b)(1) through (3) of this section.
(1) Prepared the control device operation and maintenance plan according to the requirements of Sec. 63.7800(b), including a preventative maintenance schedule and, as applicable, detailed descriptions of the corrective action procedures for baghouses and other control devices;
(2) Submitted a notification of compliance status according to the requirements in Sec. 63.7840(e), including a copy of the operation and maintenance plan; and
(3) Prepared a site-specific monitoring plan according to the requirements in Sec. 63.7831(a). [68 FR 27663, May 20, 2003, as amended at 71 FR 39586, July 13, 2006]
Continuous Compliance Requirements