(a) If you use a floating roof according to Sec. 63.7910(b)(1), you must meet requirements in paragraphs (a)(1) and (2) of this section.
(1) Measure the seal gaps at least annually according to the requirements in Sec. 63.1047(b)(1).
(2) Visually inspect the floating roof at least annually according to the requirements in Sec. 63.1047(b)(2).
(b) If you use a cover vented to a control device according to Sec. 63.7910(b)(1) or (2), you must meet requirements in paragraphs (b)(1) and (2) of this section.
(1) You must visually inspect the cover and its closure devices for defects according to the requirements in Sec. 63.1047(c).
(2) You must monitor and inspect the closed vent system and control device according to the requirements in Sec. 63.7927 that apply to you.
(c) If you use a pressurized separator that operates as a closed system according to Sec. 63.7910(b)(3), you must visually inspect each pressurized separator and closure devices for defects at least annually to ensure they are operating according to the design requirements in Sec. 63.1045(b).