CFR /  Title 48  /  Part 243  /  243.204-70-6 Allowable profit.

When the final price of an unpriced change order is negotiated after a substantial portion of the required performance has been completed, the head of the contracting activity shall ensure the profit allowed reflects--

(a) Any reduced cost risk to the contractor for costs incurred during contract performance before negotiation of the final price;

(b) The contractor's reduced cost risk for costs incurred during performance of the remainder of the contract; and

(c) The extent to which costs have been incurred prior to definitization of the contract action (see 215.404-71-3(d)(2)). The risk assessment shall be documented in the contract file. [75 FR 48277, Aug. 10, 2010]