CFR /  Title 48  /  Part 4  /  4.804-4 Physically completed contracts.

(a) Except as provided in paragraph (b) below, a contract is considered to be physically completed when--

(1)(i) The contractor has completed the required deliveries and the Government has inspected and accepted the supplies;

(i) The contractor has completed the required deliveries and the Government has inspected and accepted the supplies;

(ii) The contractor has performed all services and the Government has accepted these services; and

(iii) All option provisions, if any, have expired; or

(2) The Government has given the contractor a notice of complete contract termination.

(b) Rental, use, and storage agreements are considered to be physically completed when--

(1) The Government has given the contractor a notice of complete contract termination; or

(2) The contract period has expired. [48 FR 42113, Sept. 19, 1983, as amended at 72 FR 27383, May 15, 2007]