CFR /  Title 30  /  Part 250  /  Sec. 250.1151 How often must I conduct well production tests?

(a) You must conduct well production tests as shown in the following table: ------------------------------------------------------------------------

And you must submit to the

(1) A well-flow potential test on all new, Form BSEE-0126, Well

recompleted, or reworked well completions Potential Test Report,

within 30 days of the date of first along with the supporting

continuous production, data as listed in the table

in Sec. 250.1167, within

15 days after the end of

the test period.(2) At least one well test during a Results on Form BSEE-0128,

calendar half-year for each producing Semiannual Well Test

completion, Report, of the most recent

well test obtained. This

must be submitted within 45

days after the end of the

calendar half-year.------------------------------------------------------------------------

(b) You may request an extension from the Regional Supervisor if you cannot submit the results of a semiannual well test within the specified time.

(c) You must submit to the Regional Supervisor an original and two copies of the appropriate form required by paragraph (a) of this section; one of the copies of the form must be a public information copy in accordance with Sec. Sec. 250.186 and 250.197, and marked ``Public Information.'' You must submit two copies of the supporting information as listed in the table in Sec. 250.1167 with form BSEE-0126.