Code of Federal Regulations (alpha)

CFR /  Title 30  /  Part 250  /  Sec. 250.465 When must I submit an Application for Permit to Modify (APM)

(a) You must submit an APM (form BSEE-0124) or an End of Operations Report (form BSEE-0125) and other materials to the Regional Supervisor as shown in the following table. You must also submit a public information copy of each form. ------------------------------------------------------------------------

(1) Intend to revise Submit form BSEE-0124 Receive written or oral

your drilling plan, or request oral approval from the

change major drilling approval, District Manager before

equipment, or you begin the intended

plugback, operation. If you get an

approval, you must

submit form BSEE-0124 no

later than the end of

the 3rd business day

following the oral

approval. In all cases,

or you must meet the

additional requirements

in paragraph (b) of this

section.(2) Determine a well's Immediately Submit a Submit a plat certified

final surface form BSEE-0124, by a registered land

location, water surveyor that meets the

depth, and the rotary requirements of Sec.

kelly bushing 250.412.

elevation,(3) Move a drilling Submit forms BSEE- Submit appropriate copies

unit from a wellbore 0124 and BSEE-0125 of the well records.

before completing a within 30 days after

well, the suspension of

wellbore operations,------------------------------------------------------------------------

(b) If you intend to perform any of the actions specified in paragraph (a)(1) of this section, you must meet the following additional requirements:

(1) Your APM (Form BSEE-0124) must contain a detailed statement of the proposed work that would materially change from the approved APD. The submission of your APM must be accompanied by payment of the service fee listed in Sec. 250.125;

(2) Your form BSEE-0124 must include the present status of the well, depth of all casing strings set to date, well depth, present production zones and productive capability, and all other information specified; and

(3) Within 30 days after completing this work, you must submit form BSEE-0124 with detailed information about the work to the District Manager, unless you have already provided sufficient information in a Well Activity Report, form BSEE-0133 (Sec. 250.468(b)).